Miller/Wagner: Working on the Bypass

By October 15, 2020Project Updates

It’s only been a week since the roundabout was partially reopened but our contractor is already making steady progress on the Miller Road bridge replacement project over Honey Creek, west of the roundabout.

This week, our contractor’s crews are installing the bypass structures to keep creek water out of the work area. They are also removing old pavement and grading areas in preparation for road reconstruction.

Questions? Contact Nate Murphy, project manager and bridge engineer, (734) 327-6647, murphyn@wcroads.org.