Harris Road is Off to a Good Start!

The Harris Road reconstruction project is officially underway!  Here’s a brief update on our progress to date:

  • Water main installation is underway by the Washtenaw County Road Commission (WCRC) road contractor.
  • DTE – Gas is working to complete the gas main installation and customer service connections.
  • The WCRC road contractor is scheduled to begin construction of the storm sewer and drainage structures in the next week.
  • Mailboxes will soon be temporarily relocated by the road contractor.  Your mailbox will be located outside the work area near the closest intersection.

Feel free to contact Matt MacDonell, WCRC project manager at [email protected] with any questions. Have a great weekend!

Back fill being delivered for the water mainline trench on Harris Road.

Contractors working on the water mainline installation on Harris Road.

Washtenaw County Road Commission
Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.