Full Steam Ahead on Chubb Road

By October 17, 2019Project Updates

Last week, our contractors started reconstructing Chubb Road between 5 Mile Road and 6 Mile Road in Salem Township and they are making great progress! Multiple crews are working on different stages of construction from storm pipe installation to cutting the grade and placing the aggregate base.

The final layer of asphalt will be placed on 5 Mile Road between Chubb Road and Napier Road this weekend if the weather cooperates.

For specific questions on this project, contact Mark McCulloch, senior project manager, mccullochm@wcroads.org,  (734) 327-6679.

Cutting the grade on Chubb Road

Laying the aggregate base on Chubb Road

Installing the storm sewer on Chubb Road