E. Delhi Rd and Maple (Foster) Rd Bridges: Enclosure Going Up

E. Delhi Rd Bridge (Scio Twp): The E. Delhi Rd Bridge officially closed late last week and we are off to a good start! Our contractor is currently working to install the enclosure around the lower portion of the bridge. This enclosure will control the dust while the contractor sandblasts the structure for paint removal, which is expected to begin later today.

Just a reminder the bridge remains closed to all traffic, including river traffic and non-motorized users, until rehabilitation is complete. Click here for the detour route.

photo of the bridge enclosure

Pictured above is the enclosure being installed on the lower portion of the E. Delhi Rd Bridge in Scio Township.

 

Maple (Foster) Rd Bridge (Ann Arbor Twp): We continue to make great progress on the Maple (Foster) Rd Bridge Rehabilitation Project. Last week our contractor poured the concrete for the new curb and spillways, which are being installed to prevent material erosion around the base of the bridge.

Just a reminder the bridge remains closed to all traffic, including river traffic and non-motorized users, until rehabilitation is complete. Click here for the detour route. 

Questions? Please contact Nate Murphy, project manager, (734) 327-6647, [email protected].

photo of concrete spillway to prevent erosion

Pictured above is one of the concrete spillways recently poured on the Maple (Foster) Rd Bridge in Ann Arbor Township.