Dennison Rd: Word on the Bridge

We are making great headway at the Dennison Rd Bridge Project in York Township. The concrete barrier on the east side of the bridge was poured earlier this week and the forms were removed yesterday.

Word on the bridge is that our contractors are currently installing the steel railing and then will be preparing the work zone for road crews to begin paving the bridge approaches. We are hoping that paving will begin sometime next week, pending our contractor’s schedule and the weather.

Questions? Contact Nate Murphy, project manager and bridge engineer, (734) 327-6647, [email protected].

photo of new steel railing

Pictured above is the new steel railing that is currently being installed at the Dennison Rd Bridge Project.