We are making great headway at the Dennison Rd Bridge Project in York Township. Great news–the concrete bridge deck has finally finished curing.
The concrete bridge approach on the north side of the bridge and the concrete barrier on the west side of the bridge were both poured last week and the forms were removed. The forms are now being installed for the concrete barrier on the east side of the bridge. We are currently pouring the concrete for the bridge approach on the south side of the bridge.
Questions? Contact Nate Murphy, project manager and bridge engineer, (734) 327-6647, murphyn@wcroads.org.