Dennison Rd: Seal the Surface

By September 1, 2021Project Updates

We continue to make great progress at the Dennison Rd Bridge Project in York Township.

Last week our contractor finished paving the asphalt bridge approaches and installing the guardrail. This week they are working on applying the pavement markings. There are just a few items left to be completed before we can reopen the bridge, including applying a paint-like sealant to the new concrete bridge.

Please be aware that the bridge is still closed to traffic. We will send out an advisory when the bridge officially reopens to traffic.

Questions? Contact Nate Murphy, project manager and bridge engineer, (734) 327-6647, [email protected].

photo of guardrail

Pictured above is one of the guardrails that was installed last week at the Dennison Rd Bridge Project.