The Dennison Rd Bridge Project in York Township is coming along great! Our contractor continues to make great headway.

Last night, our contractor made good use of the cooler temperatures and poured the concrete for the new bridge deck. The cooler temperatures allow the concrete to cure slowly and steadily for the most desirable outcome. You may notice a pause in active work as we wait for the concrete to fully cure.

Questions? Contact Nate Murphy, project manager and bridge engineer, (734) 327-6647, murphyn@wcroads.org.

photo of overnight concrete pouring

Pictured above is the Dennison Rd Bridge Project in York Township where concrete was poured last night for the new bridge deck.