The Dennison Rd Bridge Project in York Township is steadily coming along. Last week our contractor finished pouring the concrete for the new bridge deck.
While waiting for the concrete on the deck to cure, the contractor is making headway on the bridge approaches on both sides of the bridge. On the north side they are building the forms for the concrete bridge approach to be poured.
Questions? Contact Nate Murphy, project manager and bridge engineer, (734) 327-6647, [email protected].