On Thursday, October 10, 2024, the Washtenaw County Road Commission (WCRC) reopened all lanes on westbound Jackson Rd between Jackson Industrial Dr and Myrtle Ave in Scio Township. This week,…
The contractor placed reinforced steel and is waiting for the concrete to cure on the aprons of the new structure on the Stony Creek Rd Bridge over Paint Creek between…
The week of September 23rd, the contractor for the Washtenaw County Road Commission (WCRC) laid down the final aggregate (stone) shoulders and placed the last of the pavement markings on…
The contractor for the Washtenaw County Road Commission (WCRC) is nearly finished placing the pavement markings and aggregate shoulders on N. Territorial Rd between Webster Church Rd and US-23 in…
The final placement of concrete pavement occurred the week of September 30th on Jackson Rd between Myrtle Ave and Jackson Industrial Dr in Scio Township. The newly placed concrete will…
The contractor for the Washtenaw County Road Commission (WCRC) are crushing and shaping (pulverizing) the existing surface on Metty Dr. between Jackson Rd and the cul-de-sac in Scio Township. They…
The contractor for the Washtenaw County Road Commission (WCRC) crushed and shaped (pulverized) the old asphalt on Dino Dr between Jackson Rd and the cul-de-sac in Scio Township. Next steps…
The week of September 23rd, the precast concrete structure (box culvert) was delivered earlier than scheduled by the manufacturer. This week and next week, the contractor is assembling the new…
The resurfacing project on McKernan Rd between M-52 and the end of the pavement in Sylvan Township is complete. The contractor for the Washtenaw County Road Commission (WCRC) has placed…
The resurfacing project on Brown Dr, between Aspen Blvd and M-52 in Sylvan Township, is complete! Recently, the contractor for the Washtenaw County Road Commission (WCRC) placed aggregate (stone) shoulders…