Location of roadwork:
Nixon Rd between the Ann Arbor City Limits and Pontiac Trail
Township:
Ann Arbor
When is the work being done:
2025
Description of work:
Pulverize & Pave
Impact on Traffic:
Road Closure with Detour
Funding Source(s):
Federal
Latest Updates
Paving Underway
As of September 12, 2025, Ajax Paving, the contractor working on behalf of the Washtenaw County Road Commission (WCRC), has completed the pulverizing (crushing), shaping, and compaction of the existing asphalt pavement on Nixon Rd between US-23/M-14 and Pontiac Trail in Ann Arbor Township. The resulting crushed material will serve as the base for the new hot mix asphalt (HMA) surface.
Paving of the first layer of HMA is scheduled for September 12th and 13th. Weather permitting, the contractor will continue by placing the second (top) layer of HMA.
Road Closure Reminder:
Nixon Road remains closed to through traffic between US-23/M-14 and Pontiac Trail. This closure also affects Warren Road—traffic on Warren Road cannot access Nixon Road.
Access along Nixon Road will be maintained for local traffic, including residents who live within the closure area.

Pictured above paving on Nixon Rd between US-23/M-14 and Pontiac Trail in Ann Arbor Township
WHEN: Tuesday, September 2, 2025
WHERE: Nixon Rd between US-23 and Pontiac Trail in Ann Arbor Township
WHY: Pulverizing and paving
BACKGROUND: On Tuesday, September 2, 2025, the Washtenaw County Road Commission (WCRC) will close the intersection of Nixon Rd and Warren Rd in Ann Arbor Township for pulverization and paving. Also on Friday, September 5, 2025, the contractor for WCRC will close Nixon Rd between US-23 and Pontiac Trail in Ann Arbor Township for the same roadwork.
The road improvements are expected to take approximately four weeks to complete. However, all dates are tentative and subject to change due to weather conditions.
During this daytime roadwork through-traffic will be prohibited, and alternate routes are advised. Local access for properties within the road closure will be maintained, however, delays are possible.
DETOUR: Detour map
CONTACT: If you have any questions concerning this work, please contact Kevin Dubnicki, Project manager, (734) 327-6693, or via email at [email protected]
ISSUE DATE: 09/03/25
WHEN: Tuesday, September 2, 2025
WHERE: Nixon Rd between US-23 and Pontiac Trail in Ann Arbor Township
WHY: Pulverizing and paving
BACKGROUND: On Tuesday, September 2, 2025, the Washtenaw County Road Commission (WCRC) will close the east side of the intersection of Nixon Rd and Warren Rd in Ann Arbor Township for culvert repairs. The week of September 8, 2025, the contractor for WCRC will close Nixon Rd between US-23 and Pontiac Trail in Ann Arbor Township for pulverizing and paving. Through traffic crossing Nixon will not be allowed on Warren Road.
The road improvements are expected to take approximately four weeks to complete. However, all dates are tentative and subject to change due to weather conditions.
During this daytime roadwork through-traffic will be prohibited, and alternate routes are advised. Local access for properties and businesses within the road closure will be maintained, however, delays are possible.
DETOUR: Detour map
CONTACT: If you have any questions concerning this work, please contact Kevin Dubnicki, Project manager, (734) 327-6693, or via email at [email protected]
ISSUE DATE: 08/27/25
WHEN: Friday, February 14, 2025, at 11 a.m.
WHERE: Online: https://bit.ly/wcrcprojectmeeting
By Touchtone Phone: (929) 205-6099, Meeting ID: 879 2332 8754
WHY: The Washtenaw County Road Commission (WCRC) will hold a virtual project information meeting regarding the planned County-wide Resurfacing Program taking place during the 2025 construction season.
During construction, traffic will be maintained under lane restrictions and flagging operations. During specific construction activities, the road may be closed, and a detour will be posted. WCRC estimates it will take approximately two/three weeks, on average, to complete each project, weather pending.
The virtual public meeting will be held via Zoom Friday, February 14, 2025, at 11 a.m. There will be a brief presentation followed by time for questions from the audience. A recording of the meeting will be posted to the project web page after the meeting.
Click here to learn more about joining the virtual meeting.
CONTACT: If you have any questions concerning these project, please contact Felix Weber-Bailey, Project Manager, (734) 327-6654, email [email protected], Kevin Dubnicki, Project Manager, (734) 327 -6693, email [email protected] and Ken Harris, Superintendent, (734) 327-6696, email [email protected]
WCRC will provide necessary reasonable auxiliary aids and services, such as signers for the hearing impaired and audiotapes or printed material being presented at the meeting, to individuals with disabilities upon a 5-business day notice. Individuals with disabilities requiring auxiliary aids or services should contact Tiffany Oliphant, communications manager, by phone (734) 327-6646 or by email [email protected].
ISSUE DATE: 02/04/25
The Washtenaw County Road Commission (WCRC) is excited to announce a $9.4 million investments in improving approximately 37 miles of paved and unpaved roads across Washtenaw County during the 2025 construction season. These important projects are made possible through a combination of funding sources, including the 2025-2028 Four-Year County-Wide Roads and Non-motorized Millage, Federal Funds, Township partnerships, and Michigan Transportation Funds (MTF).
“This year’s resurfacing program is just one of the ways WCRC is committed to protecting the county’s transportation infrastructure,” said Brent Schlack, P.E., Director of Engineering and County Highway Engineer. “The successful completion of these critical projects requires a blend of resources and collaboration.”
Construction is slated to begin in mid-April and will continue through the fall of 2025, weather permitting. As part of this program, WCRC will also undertake necessary forestry work to maintain the safety and integrity of the roadways.
For a list of the specific projects, funding details, and anticipated traffic impacts, please refer to the links provided below for each project location.
Motorists will experience road closures with detours, daytime road closures, lane restrictions, and flagging operations. WCRC will maintain access for residents who live or work within the project limits during construction.
WCRC will host a virtual public information meeting regarding the County-wide Resurfacing projects on February 14, 2025. WCRC will post project updates online at wcroads.org. Residents can subscribe to road work advisories and project updates here.
For specific questions on these projects, contact Felix Weber-Bailey, Project Manager, (734) 327-6654, email [email protected], Kevin Dubnicki, Project Manager, (734) 327 -6693, email [email protected] and Ken Harris, Superintendent, (734) 327-6696, email [email protected].
Pictured is a map of our 2025 County-wide Resurfacing Program.