Grass Lake Rd

Location of roadwork:
Grass Lake Rd between Sylvan Rd and M-52

Township:
Sharon

When is the work being done:
2026

Description of work:
Mill & Resurfacing

Impact on Traffic:
Flagging

Funding Source(s):
Four-Year Road and Non-Motorized Path Millage, Michigan Transportation Fund (MTF)

Latest Updates

July 14, 2026 Project Update #2: Grass Lake Rd Resurfacing (Sharon Twp)

On July 13, 2026, the contractor working on behalf of the Washtenaw County Road Commission (WCRC), completed the permanent pavement markings on Grass Lake Rd between Sylvan Rd and M-52 in Sharon Township.  

If you have questions, contact Felix Weber, Project Manager, (734) 327-6689, or via email at [email protected]. 

Pictured above is completed pavement markings on Grass Lake Rd between Sylvan Rd and M-52 in Sharon Township. 
July 1, 2026 Project Update #1: Grass Lake Rd Resurfacing (Sharon Twp)

On June 24, 2026, the contractor working on behalf of the Washtenaw County Road Commission (WCRC) began milling (removing) the existing road surface on Grass Lake Rd between Sylvan Rd and M-52 in Sharon Township. The milling was completed on June 25th, with asphalt paving starting the next day. On June 30th, the contractor completed the paving of Grass Lake Rd between Sylvan Rd and M-52 in Sharon Township with a new asphalt surface. 

In the coming weeks, new permanent pavement markings will be added to the freshly paved surface. 

If you have questions, contact   Felix Weber, Project Manager, (734) 327-6689, or via email at [email protected]. 

Pictured above are milling operations on Grass Lake Rd between Sylvan Rd and M-52 in Sharon Township.
Pictured above is asphalt paving on Grass Lake Rd between Sylvan Rd and M-52 in Sharon Township.
June 25, 2026 Extended Intermittent Lane Restrictions: Grass Lake Rd (Sharon Twp)

WHEN: Friday, June 12, 2026

WHERE: Grass Lake Rd between Sylvan Rd and M-52 in Sharon Township

 WHY: Milling & resurfacing

 BACKGROUND: The Washtenaw County Road Commission (WCRC) has extended the intermittent lane restrictions by one week on Grass Lake Rd between Sylvan Rd and M-52 in Sharon Township for milling and resurfacing.

The work started on Friday, June 12, 2026, and will now take approximately three weeks to complete, subject to weather changes.

Although the road will remain open, delays are likely to be due to lane restrictions. Motorists should consider alternative routes.

CONTACT: If you have any questions concerning this project, please contact Felix Weber, Project Manager, (734) 327-6654, email [email protected].

ISSUE DATE: 06/25/2026

June 16, 2026 Extended Lane Restrictions: Grass Lake Rd (Sharon Twp)

WHEN: Friday, June 12, 2026 

WHERE: Grass Lake Rd between Sylvan Rd and M-52 in Sharon Township 

WHY: Milling & Resurfacing  

BACKGROUND: The Washtenaw County Road Commission (WCRC) has extended the intermittent lane restrictions by one week on Grass Lake Rd between Sylvan Rd and M-52 in Sharon Township for milling and resurfacing. 

The work started on Friday, June 12, 2026, and will now take approximately two weeks to complete, subject to weather changes. 

Although the road will remain open, delays are likely to be due to lane restrictions. Motorists should consider alternative routes. 

CONTACT: If you have any questions concerning this project, please contact Felix Weber, Project Manager, (734) 327-6654, email [email protected]. 

ISSUE DATE: 06/16/2026 

June 10, 2026 Lane Restrictions: Grass Lake Rd (Sharon Twp)

WHEN: Friday, June 12, 2026

WHERE:Grass Lake Rd between Sylvan Rd and M-52 in Sharon Township

WHY:Milling & Resurfacing

BACKGROUND: On Friday, June 12, 2026, The Washtenaw County Road Commission (WCRC) will perform asphalt resurfacing on Grass Lake Rd between Sylvan Rd and M-52 in Sharon Township.

The road will not be closed to traffic, but delays are likely due to intermittent lane restrictions.

The asphalt resurfacing is expected to take approximately nine days. However, all dates are tentative and subject to change due to weather conditions.

CONTACT: If you have any questions concerning this project, please contact Felix Weber, Project Manager, (734) 327-6654, email [email protected].

ISSUE DATE:06/10/26

March 17, 2026 Extended Daytime Road Closure: Grass Lake Rd (Sharon Twp)

WHEN: Monday, March 16, 2026

WHERE: Grass Lake Rd between Sylvan Rd and M-52 in Sharon Township

WHY: Drainage work

BACKGROUND: The Washtenaw County Road Commission (WCRC) has extended the daytime road closure Grass Lake Rd between Sylvan Rd and M-52 in Sharon Township for drainage work by three days.

The work originally started on Monday, March 16, 2026, and now will be completed in five days, subject to weather changes.

CONTACT: If you have any questions concerning this work, please contact Ken Harris, superintendent of maintenance, (734) 327-6696 or via email at [email protected].

ISSUE DATE: 03/17/2026

March 16, 2026 Daytime Road Closure: Grass Lake Rd (Sharon Twp)

WHEN: Monday, March 16, 2026

WHERE: Grass Lake Rd between Sylvan Rd and M-52 in Sharon Township

WHY: Drainage work

BACKGROUND:  On Monday, March 16, 2026, the Washtenaw County Road Commission (WCRC) will perform drainage work on Grass Lake Rd between Sylvan Rd and M-52 in Sharon Township.

The drainage work is expected to take approximately two days to complete. However, all dates are tentative and subject to change due to weather conditions.

CONTACT: If you have any questions concerning this work, please contact Ken Harris, superintendent of maintenance, (734) 327-6696 or via email at [email protected].

ISSUE DATE: 03/16/26

March 5, 2026 Daytime Road Closure: Grass Lake Rd (Sharon Twp)

WHEN: Monday, March 9, 2026

WHERE: Grass Lake Rd between Sylvan Rd and M-52 in Sharon Township

WHY:  Drainage work

BACKGROUND: On Monday, March 9, 2026, the Washtenaw County Road Commission (WCRC) will perform drainage work on Grass Lake Rd between Sylvan Rd and M-52 in Sharon Township.

The drainage work is expected to take approximately three days to complete. However, all dates are tentative and subject to change due to weather conditions.

Motorists can expect delays in the area.

CONTACT: If you have any questions concerning this work, please contact Ken Harris, superintendent of maintenance, (734) 327-6696 or via email at [email protected].

ISSUE DATE: 03/05/26

February 12, 2026 Daytime Road Closure: Grass Lake Rd (Sharon Twp)

WHEN: Thursday, February 12, 2026

WHERE: Grass Lake Rd between Sylvan Rd and M-52 in Sharon Township

WHY: Forestry

BACKGROUND: On Thursday, February 12, 2026, the Washtenaw County Road Commission (WCRC) will perform forestry work on Grass Lake Rd between Sylvan Rd and M-52 in Sharon Township.

The road improvements are expected to take approximately one day to complete. However, all dates are tentative and subject to change due to weather conditions.

CONTACT:  If you have any questions concerning this work, please contact Ken Harris, superintendent of maintenance, (734) 327-6696 or via email at [email protected].

ISSUE DATE:  02/12/26

February 12, 2026 Road Reopen: Grass Lake Rd (Sharon Twp)

WHEN: Wednesday, February 11, 2026

WHERE: Grass Lake Rd between Sylvan Rd and M-52 in Sharon Township

WHY:  Forestry work–completed

BACKGROUND: On Wednesday, February 11, 2026, the Washtenaw County Road Commission (WCRC) reopened Grass Lake Rd between Sylvan Rd and M-52 in Sharon Township.

CONTACT: If you have any questions concerning this work, please contact Ken Harris, Superintendent of Maintenance, (734) 327-6696, or via email at [email protected]

ISSUE DATE: 02/12/26

February 11, 2026 Daytime Road Closure: Grass Lake Rd (Sharon Twp)

WHEN: Wednesday, February 11, 2026

WHERE: Grass Lake Rd between Sylvan Rd and M-52 in Sharon Township

WHY: Forestry

BACKGROUND: On Wednesday, February 11, 2026, the Washtenaw County Road Commission (WCRC) will perform forestry work on Grass Lake Rd between Sylvan Rd and M-52 in Sharon Township.

The road improvements are expected to take approximately one day to complete. However, all dates are tentative and subject to change due to weather conditions.

CONTACT:  If you have any questions concerning this work, please contact Ken Harris, superintendent of maintenance, (734) 327-6696 or via email at [email protected].

ISSUE DATE:  02/11/26

February 10, 2026 Road Reopen: Grass Lake Rd (Sharon Twp)

WHEN: Tuesday, February 10, 2026

WHERE: Grass Lake Rd between Sylvan Rd and M-52 in Sharon Township

WHY: Forestry work–completed

BACKGROUND: On Tuesday, February 10, 2026, the Washtenaw County Road Commission (WCRC) reopened Grass Lake Rd between Sylvan Rd and M-52 in Sharon Township.

CONTACT: If you have any questions concerning this work, please contact Ken Harris, Superintendent of Maintenance, (734) 327-6696, or via email at [email protected]

 ISSUE DATE: 02/10/26

February 5, 2026 Daytime Road Closure: Grass Lake Rd (Sharon Twp)

WHEN: Monday, February 9, 2026

WHERE: Grass Lake Rd between Sylvan Rd and M-52 in Sharon Township

WHY: Forestry

BACKGROUND: On Monday, February 9, 2026, the Washtenaw County Road Commission (WCRC) will perform forestry work on Grass Lake Rd between Sylvan Rd and M-52 in Sharon Township.

The road improvements are expected to take approximately two days to complete. However, all dates are tentative and subject to change due to weather conditions.

CONTACT: If you have any questions concerning this work, please contact Ken Harris, superintendent of maintenance, (734) 327-6696 or via email at [email protected].

ISSUE DATE: 02/05/26

January 5, 2026 Daytime Road Closure: Grass Lake Rd (Sharon Twp)

WHEN: Tuesday, January 6, 2026

WHERE: Grass Lake Rd between Sylvan Rd and M-52 in Sharon Township

WHY:  Forestry

BACKGROUND:  On Tuesday, January 6, 2026, the Washtenaw County Road Commission (WCRC) will perform forestry work on Grass Lake Rd between Sylvan Rd and M-52 in Sharon Township.

The road improvements are expected to take approximately eleven days to complete. However, all dates are tentative and subject to change due to weather conditions.

DETOUR:  Detour map

CONTACT: If you have any questions concerning this work, please contact Jared Powers, Assistant Superintendent of Maintenance, (734) 327-6650, or via email at [email protected]

ISSUE DATE: 01/05/26

December 19, 2025 Virtual Public Meeting: 2026 Countywide Resurfacing Program

WHEN: Wednesday, January 14, 2026, at 11 a.m.

WHERE: Online: https://bit.ly/wcrcprojectmeeting

By Touchtone Phone: (929) 205-6099, Meeting ID: 879 2332 8754

WHY: The Washtenaw County Road Commission (WCRC) will hold a virtual project information meeting regarding the planned County-wide Resurfacing Program taking place during the 2026 construction season.

During construction, traffic will be maintained under lane restrictions and flagging operations. During specific construction activities, the road may be closed, and a detour will be posted. WCRC estimates it will take approximately two/three weeks, on average, to complete each project, weather pending.

The virtual public meeting will be held via Zoom Wednesday, January 14, 2026, at 11 a.m. There will be a brief presentation followed by time for questions from the audience. A recording of the meeting will be posted to the project web page after the meeting.

Click here to learn more about joining the virtual meeting.

CONTACT: If you have any questions concerning these project, please contact Felix Weber, Project Manager, (734) 327-6654, email [email protected], Jane Allen, Project Manager, (734) 327 –6691, email [email protected] and Ken Harris, Superintendent, (734) 327-6696, email [email protected]

WCRC will provide necessary reasonable auxiliary aids and services, such as signers for the hearing impaired and audiotapes or printed material being presented at the meeting, to individuals with disabilities upon a 5-business day notice. Individuals with disabilities requiring auxiliary aids or services should contact Tiffany Oliphant, communications manager, by phone (734) 327-6646 or by email [email protected].

ISSUE DATE: 12/19/25

December 12, 2025 Project Announcement: 2026 Resurfacing Program (County-wide)

The Washtenaw County Road Commission (WCRC) is committed to investing almost $8.2 million solely dedicated to the enhancement and improvement of roughly 30 miles of paved and unpaved roads across Washtenaw County during the 2026 construction season. This work is supported through 2025-2028 Four-Year County-Wide Roads and Non-motorized Millage, Federal Funds, Township partnerships, and Michigan Transportation Funds (MTF).

“This 2026 Resurfacing Program is another step in our ongoing effort to revitalize and upgrade our transportation network,” said Brent Schlack, P.E., Director of Engineering and County Highway Engineer. “These improvements happen thanks to teamwork, smart planning, and shared resources.”

WCRC will host a virtual public information meeting regarding the County-wide Resurfacing projects on January 14, 2026.

Roadwork is set to kick-off in mid-April and continue into fall 2026, weather permitting. The organization will also complete forestry work along project routes to help keep the roadways safe and resilient.

Drivers can expect the usual construction-season mix of detours, daytime closures, lane shifts, and flagging operations, though access will remain open for those who live or work within the project areas.

Looking for details? Project maps, funding breakdowns, and expected traffic impacts are available at the links below.

 

WCRC will post project updates online at wcroads.org. Residents can subscribe to road work advisories and project updates here.

For specific questions on these projects, contact Felix Weber-Bailey, Project Manager, (734) 327-6654, email [email protected], Jane Allen, Project Manager, (734) 327 -6691, email [email protected] and Ken Harris, Superintendent, (734) 327-6696, email [email protected].

Contact information:
Felix Weber
    • (34) 327-6689
Receive Updates on the Project
Subscribe to Project Updates
Washtenaw County Road Commission
Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.