WHEN: Resuming on Monday, June 13, 2022
WHERE:
- Maple Rd between the City of Saline and Ann Arbor-Saline Rd on the border of Lodi and Pittsfield Townships
- Ellsworth Rd between Maple Rd and State Rd in Pittsfield Township
- Lohr Cir in Pittsfield Township
WHY: Preventative maintenance – chip seal
BACKGROUND: On Monday, June 13, 2022, the Washtenaw County Road Commission (WCRC) will resume its preventative maintenance chip seal project on:
- Maple Rd between the City of Saline and Ann Arbor-Saline Rd on the border of Lodi and Pittsfield Townships. The road will not be closed but delays are likely due to lane restrictions. Motorists are advised to seek an alternate route.
- Ellsworth Rd between Maple Rd and State Rd in Pittsfield Township
- Lohr Circle in Pittsfield Township
During a daytime road closure, access will be provided to emergency services, school buses and residents who live, work or own property within the work zone. The roads will reopen at the end of each day and remain open until work resumes the following morning.
Chip seal work in this area is expected to take approximately two days to complete. However, all dates are tentative and subject to change due to weather conditions.
Drivers are advised to lower their speeds to 35 mph while the stone settles.
WCRC will return to this area in a few weeks to apply a fog seal on top of the chip seal and place permanent pavement markings.
CONTACT: If you have any questions, please contact Ken Harris, superintendent of maintenance, (734) 327-6696 or via email at [email protected].
ISSUE DATE: 06/09/22