Project Update #4 – Tyler Rd Road Reconstruction Project (Ypsilanti Twp)

By April 11, 2025Project Updates

This week, WCRC’s contractor installed upgraded stormwater systems around the dam. WCRC also worked on upgrading drainage along Tyler Rd, North and East of the project site to divert flow away from the dam in the future.

Next week, the contractor will clean up the ditch left behind by the initial rain event and prepare the area for installation of a geocellular confinement system on the ridge adjacent to the dam.

WCRC will continue to send out updates as the project progresses. Have questions? Contact Neeko Robison, Project Manager – Design & Construction, (734) 327-6660, or via email at [email protected]