On Monday, October 27, 2025, the Washtenaw County Road Commission (WCRC), began removing and replacing the culvert on Judd Rd between Warner Rd and Platt Rd in York Township.  

Crews have started to build the box culvert and will start excavating and removing the old culvert this week.  

The week of November 3, crews will finish backfilling, headwall installation and restoration. Once the project is complete, the road will be re-opened to traffic. WCRC will send out updates as the project progresses. 

WCRC is able to perform this project thanks to the American Rescue Plan Act (ARPA) and its partnership with the Washtenaw County Water Resources Commissioner’s Office and the Township.   

If you have any questions regarding this project, contact Ken Harris, Superintendent of Maintenance, at (734) 327-6696, or via email at [email protected]. 

Pictured above is the completed box culvert before installation on Judd Rd between Warner Rd and Platt Rd in York Township. 

Pictured above is the new box culvert installed and awaiting backfill on Judd Rd between Warner Rd and Platt Rd in York Township. 

 

Washtenaw County Road Commission
Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.