Pontiac Tr and 7 Mile Rd: Prepping for Pavement

Thanks to a relatively dry but hot weather window, our contractor continues to make great progress on the roundabout at the intersection of Pontiac Trail and 7 Mile Road in Salem Township. The concrete curb and gutter were poured last week. Once the concrete cures, they will pour concrete inside the center island and splitter islands. Our contractor is also grading the area in preparation for asphalt paving.

If you have any questions, please contact Mark McCulloch, senior project manager, (734) 327-6679, [email protected].

contractors grading roundabout

Our contractors have started grading in preparation for asphalt.

Washtenaw County Road Commission
Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.