Lane Restrictions: Plymouth Rd (Ann Arbor & Superior Twps)

By February 22, 2024Road Advisories

WHEN: Monday, February 19, 2024

WHERE: Plymouth Rd between Earhart Rd and M-153 in Ann Arbor & Superior Townships

WHY: Traffic signal work

BACKGROUND: On Monday, February 19, 2024, the Washtenaw County Road Commission (WCRC) began traffic signal work on Plymouth Rd between Earhart Rd and M-153 in Ann Arbor & Superior Townships.

The road is not closed to traffic, but delays are likely due to lane restrictions. WCRC encourages motorists, emergency services and others to use an alternate route.

The traffic signal work is expected to take three weeks. However, all dates are tentative and subject to change due to weather conditions.

CONTACT: If you have any questions concerning this work, please contact Elena Yadykina, Project Manager, (734) 327-6675, or via email at [email protected]

ISSUE DATE: 02/22/24