WHEN: Starting Monday, November 23, 2020
WHERE: Pleasant Lake Road between Zeeb Road and Ann Arbor-Saline Road in Lodi Township
WHY: Guardrail Installation
BACKGROUND: On Monday, November 23, 2020, a contractor for the Washtenaw County Road Commission will be installing guardrail in specific sections of Pleasant Lake Road between Zeeb Road and Ann Arbor-Saline Road in Lodi Township.
The road will not be closed to traffic, but delays are likely due to lane restrictions. WCRC encourages motorists, emergency services and others to use an alternate route.
The work is expected to take approximately 10 days. However, all dates are tentative and subject to change due to weather conditions.
CONTACT: If you have any questions, please contact James Hui, (734) 327-6660, or via email at [email protected]
ISSUE DATE: 11/20/20