WHEN: On Thursday, June 22, 2023
WHERE: Mast Rd between Huron River Dr and Strawberry Lake Rd in Webster Township
WHY: Preventative maintenance – chip seal
BACKGROUND: On Thursday, June 22, 2023, the Washtenaw County Road Commission (WCRC) will begin a preventative maintenance chip seal project on Mast Rd between Huron River Dr and Strawberry Lake Rd in Webster Township.
The road will not be closed to traffic, but delays are likely. WCRC encourages motorists, emergency services and others to use an alternate route.
The majority of the work will be completed on Thursday, June 22, and the remainder will be completed in the coming weeks. However, all dates are tentative and subject to change due to weather conditions.
CONTACT: If you have any questions concerning this work, please contact Ken Harris, superintendent of maintenance, at (734) 327-6696 or via email at [email protected].
ISSUE DATE: 06/22/23