Lane Restrictions: Maple Rd (Lodi, Pittsfield Twps)

By August 19, 2021Road Advisories

WHEN: Starting on Monday, August 23, 2021

WHERE: Maple Rd between Textile Rd and Ann Arbor-Saline Rd in Lodi and Pittsfield Townships

WHY: Road resurfacing

BACKGROUND: Starting on Monday, August 23, 2021, the Washtenaw County Road Commission (WCRC) will begin a road resurfacing project on Maple Rd between Textile Rd and Ann Arbor-Saline Rd in Lodi and Pittsfield Townships.

The road will not be closed to traffic, but delays are likely due to lane closures. WCRC encourages motorists, emergency services and others to use an alternate route.

The road improvement is expected to take approximately 2 weeks. However, all dates are tentative and subject to change due to weather conditions.

CONTACT: If you have any questions, please contact Mike Bernbeck, project manager (734) 327-6654, or via email at [email protected].

ISSUE DATE: 08/19/21