Lane Restrictions: Leforge Rd (Superior Twp)

By August 25, 2022Road Advisories

WHEN: Starting on Monday, August 29, 2022

WHERE: Leforge Rd between Clark Rd and Geddes Rd in Superior Township

WHY: Road resurfacing

BACKGROUND: Starting on Monday, August 29, 2022, the Washtenaw County Road Commission (WCRC) will begin a road resurfacing project on Leforge Rd between Clark Rd and Geddes Rd in Superior Township.

The road will not be closed to traffic, but delays are likely due to lane closures. WCRC encourages motorists, emergency services and others to use an alternate route.

The road resurfacing is expected to take approximately 4 – 6 weeks to complete. However, all dates are tentative and subject to change due to weather conditions.

CONTACT: If you have any questions, please contact James Hui, project manager, (734) 327-6660, or via email at [email protected].

ISSUE DATE: 08/25/22