WHEN: Monday, August 17, 2026
WHERE: Cherry Hill Rd Bridge, over Fleming Creek, between Gale Rd and Plymouth Rd in Superior Township
WHY: Silane treatment for bridge
BACKGROUND: On Monday, August 17, 2026, expect lane closures on the Cherry Hill Rd Bridge in Superior Township for silane treatment.
The bridge will not be closed to traffic. The northbound lane closures will occur approximately between 7 am – noon and the southbound lane closures will occur approximately from noon – 5pm. Flaggers will be present in the work zone.
The road work is expected to take approximately one day. However, all dates are tentative and subject to change due to weather conditions.
CONTACT: If you have any questions concerning this work, please contact Kevin Dubnicki, Project Manager, (734) 327-6693, or email [email protected]
ISSUE DATE: 08/12/2026