WHEN: Friday, August 21, 2026
WHERE: Jackson Rd between Fletcher Rd and Lima Center Rd in Lima Township
WHY: Permit work: utility work
BACKGROUND: On Friday, August 21, 2026, Consumers Energy will be performing permit work on Jackson Rd between Fletcher Rd and Lima Center Rd in Lima Township.
The road will not be closed to traffic, but delays are likely due to a lane closure.
The permit work is expected to take approximately two weeks to complete. However, all dates are tentative and subject to change due to weather conditions.
CONTACT: If you have any questions concerning this work, please contact Megan Kirk, (947) 957-3982, or via email at [email protected]