Building the forms for the concrete deck on the Sharon Valley Road Bridge

We continue to make progress on the new Sharon Valley Road Bridge in Sharon Township.

The concrete diaphragms and backwall were successfully poured in late-February. Our contractor is now working to create the forms for the concrete deck.  Once these items are in place, and if the weather cooperates, the concrete deck will be poured. After the deck has been successfully poured, the project will pause until the spring.

If you have any questions, please contact Aaron Berkholz, project manager, at (734) 327-6648 or [email protected].