WHEN: Tuesday, September 22, 2026
WHERE: Lima Center Rd between Dexter-Chelsea Rd and the Township Line in Lima Township
WHY: Limestone Resurfacing
BACKGROUND: On Tuesday, September 22, 2026, the Washtenaw County Road Commission (WCRC) will perform limestone resurfacing on Lima Center Rd between Dexter-Chelsea Rd and the Township Line in Lima Township.
The limestone resurfacing is expected to take approximately seven days to complete. However, all dates are tentative and subject to change due to weather conditions.
CONTACT: If you have any questions concerning this work, please contact Jared Powers, Assistant Superintendent of Maintenance, (734) 327-6650 or via email at [email protected].
ISSUE DATE: 09/17/26