Daytime Road Closure: Baker Rd and More (Scio, Webster, Lima Twps)

WHEN: Starting on Wednesday, August 4, 2021

WHERE: Starting on the following roads in Scio and Lima Townships:

  • Dexter-Ann Arbor Rd between City of Dexter and M-14
  • Baker Rd between I-94 and Shield Rd
  • Jackson Rd between I-94 and Steinbach Rd

Continuing on the following roads in Scio and Webster Townships:

  • Joy Rd between Mast Rd and Zeeb Rd

WHY: Preventative maintenance – fog seal

BACKGROUND: Starting on Wednesday, August 4, 2021, the Washtenaw County Road Commission (WCRC) will begin preventative maintenance fog seal projects on sections of the following roads in Scio and Lima Townships: Dexter-Ann Arbor Rd, Baker Rd and Jackson Rd.

WCRC will also continue preventative maintenance fog seal projects on sections of the following roads in Scio and Webster Townships: Joy Rd.

Fog seal is another thin layer of liquid asphalt placed on top of a recent chip seal that helps to seal in the chips and further protect the pavement.

The work on these roads is expected to be completed by the end of this week. However, all dates are tentative and subject to change due to weather conditions.

The work will be conducted under a combination of lane restrictions and daytime closures to allow the fog seal to cure. A contractor for WCRC will return to this area in a few weeks to place permanent pavement markings.

CONTACT: If you have any questions, please contact Ken Harris, superintendent of maintenance, (734) 327-6696 or via email at [email protected].

ISSUE DATE: 08/03/21