Almost Time to Pave

By October 25, 2019Uncategorized

It has been a very productive week on the Chubb Road reconstruction project in Salem Township. Our contractor continues to make great progress on the storm sewer and road base work. If the weather cooperates, paving the first layer of asphalt between the railroad tracks and 6 Mile Road is scheduled for early next week.

Right now, weather permitting, we are hoping to finish this project by the end of November. For specific questions on this project, contact Mark McCulloch, senior project manager, mccullochm@wcroads.org,  (734) 327-6679.

Chubb Road 10/25 Progress

We continue to make great progress on Chubb Road.