During the week of June 15, the contractor working on behalf of the Washtenaw County Road Commission (WCRC) began the installation of new bridge beams on the Cherry Hill Rd Bridge over Fleming Creek, between Gale Rd and Plymouth Rd in Superior Township.
Coming Up:
- Forms and steel reinforcement will be installed for the bridge deck in preparation of the concrete deck pour.
- Concrete work will be completed this week for approaches for the bridge
Cherry Hill Rd remains closed to all traffic; please follow the detour signs. WCRC will provide ongoing updates.
For specific questions regarding this project, contact Kevin Dubnicki, Project Manager, at (734) 327-6693, or via email at [email protected].

Pictured above an overhead view of the Cherry Hill Rd bridge, over Fleming Creek, in Superior Township.