Project Update #3: Ellsworth Rd Resurfacing (Pittsfield Twp)

By September 9, 2025Project Updates

On August 28th, Cadillac Asphalt, the contractor working for the Washtenaw County Road Commission (WCRC), completed placing pavement markings on Ellsworth Road between Platt Road and Carpenter Road in Pittsfield Township. As a preventative measure, foam repairs were made to stormwater basins along Ellsworth Rd. At that time, all lane closures were opened.  

Next steps: crews plan to perform some site cleanup along the project route and will place specialty pavement markings for the bike and turn lanes. Traffic will be maintained during this work. 

If you have questions about the project, contact Neeko Robison, Project Manager – Design & Construction, (734) 327-6660, or via email at [email protected]. 

Pictured above, pavement markings were placed along Ellsworth Rd in Pittsfield Township. 

Pictured above, foam repairs were performed on stormwater catch basins along Ellsworth Rd. 

Washtenaw County Road Commission
Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.