WHEN: Tuesday, July 8, 2025
WHERE: Fletcher Rd between Old US-12 and Dexter Chelsea Rd in Lima Township
WHY: Stone Hauling
BACKGROUND: On Tuesday, July 8, 2025, the Washtenaw County Road Commission (WCRC) will close Fletcher Rd between Old US-12 and Dexter Chelsea Rd in Lima Township for stone hauling.
Motorists can expect daytime road closures while crews perform this work. Residents who live or work within the project limits, and emergency vehicles will have access. WCRC encourages all other motorists to use an alternate route.
The road improvements are expected to take approximately seven days to complete. However, all dates are tentative and subject to change due to weather conditions.
CONTACT: If you have any questions concerning this work, please contact Jared Powers, Assistant Superintendent of Maintenance, (734) 327-6650, or via email at [email protected]