Project Update #7: Stony Creek Rd (Ypsilanti Twp)

The week of September 23rd, the precast concrete structure (box culvert) was delivered earlier than scheduled by the manufacturer. 

This week and next week, the contractor is assembling the new structure on the Stony Creek Rd over Paint Creek between Textile Rd and Whittaker Rd in Ypsilanti Township. Concrete will also be cast in-place for the bridge apron during the week of September 30th. All work is weather permitting. 

 It’s important to remember that Stony Creek Rd is closed between Textile and Whittaker Rd. Here is a link to the official detour. 

 WCRC will send out updates as the project progresses. Have any questions about the project? Contact Neeko Robison, Project Manager – Design & Construction, at (734) 327-6660, or via email at [email protected].    

Pictured is the bridge delivery and assembly on Stony Creek Rd over Paint Creek between Textile Rd and Whittaker Rd in Ypsilanti Township. 
Washtenaw County Road Commission
Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.