Pontiac Tr and 7 Mile Rd: Storming Along

By June 18, 2020Project Updates

One week into the closure and our contractor is making good progress at the intersection of Pontiac Trail and 7 Mile Road in Salem Township. The flashing overhead signal has been removed and work on the new storm sewer system is well underway.

As a reminder, the intersection is closed to all traffic and a detour is posted. Access to the Corner General Store is being provided from the east.

If you have any questions, please contact Mark McCulloch, senior project manager, (734) 327-6679, [email protected].

Storm sewer construction

Work on the storm sewer is well underway at the intersection of Pontiac Tr and 7 Mile Rd.