Waters Rd

Location of roadwork:
Waters Rd between Oak Valley Dr and Ann Arbor-Saline Rd

Township:
Pittsfield

When is the work being done:
2025

Description of work:
Mill & Resurfacing

Impact on Traffic:
Road Closure with Detour

Funding Source(s):
Federal

Latest Updates

October 6, 2025 Project Update #1: Waters Rd Resurfacing (Pittsfield Township)

On September 8, 2025, Cadillac Asphalt, a Michigan Department of Transportation contractor working on behalf of the Washtenaw County Road Commission (WCRC) completed the asphalt paving of Waters Rd between Oak Valley Dr and Ann Arbor-Saline Rd in Pittsfield Township. Temporary pavement markings were placed, and the road was reopened to all traffic.  

Next up: Permanent pavement markings and traffic signal detection (“wireless nodes”) will need to be completed. This portion of the project should be completed in the next few weeks.  

 If you have any questions regarding this project, please contact Kevin Dubnicki, Project manager, (734) 327-6693, or via email at [email protected]. 

Pictured above is facing west on Waters Rd between Oak Valley Dr and Ann Arbor-Saline Rd in Pittsfield Township. 

September 4, 2025 Road Closure: Waters Rd (Pittsfield Twp)

WHEN: Friday, September 5, 2025

WHERE: Waters Rd between Oak Valley Dr and Ann Arbor-Saline Rd in Pittsfield Township

WHY: Milling and resurfacing

BACKGROUND: On Friday, September 5, 2025, the Washtenaw County Road Commission (WCRC) will close Waters Rd between Oak Valley Dr and Ann Arbor-Saline Rd in Pittsfield Township for milling and asphalt resurfacing. Waters Rd between these intersections will be completely closed to all traffic.

The milling and paving work extends into the Waters Rd and Oak Valley Dr intersection. While traffic will be maintained with flagging operations at the intersection, motorists will experience delays.

The road improvements are expected to take approximately four days to complete. Waters Rd is expected to be reopened at the end of the day on Monday, September 8, 2025.

All dates are tentative and subject to change due to weather conditions.

Considering traffic volumes, motorists are urged to consider alternate routes. Access for adjacent businesses will be maintained via Ann Arbor-Saline Rd and Oak Valley Dr.

DETOUR: Detour map

CONTACT: If you have any questions concerning this work, please contact Kevin Dubnicki, WCRC Project Manager, (734) 327-6693 or [email protected].

ISSUE DATE: 09/04/25

 

August 28, 2025 Daytime Road Closure: Waters Rd (Pittsfield Twp)

WHEN: Friday, September 5, 2025

WHERE: Waters Rd between Oak Valley Dr and Ann Arbor Saline Rd in Pittsfield Township

WHY: Milling and resurfacing

BACKGROUND: On Friday, September 5, 2025, the Washtenaw County Road Commission (WCRC) will close Waters Rd between Oak Valley Dr and Ann Arbor Saline Rd in Pittsfield Township for milling and resurfacing.

The road improvements are expected to take approximately one day to complete. However, all dates are tentative and subject to change due to weather conditions.

During this daytime roadwork through-traffic will be prohibited, and alternate routes are advised. Local access for properties and businesses within the road closure will be maintained, however, delays are possible.

DETOUR: Detour map

CONTACT: If you have any questions concerning this work, please contact Kevin Dubnicki, Project manager, (734) 327-6693, or via email at [email protected]

ISSUE DATE: 08/28/25

February 4, 2025 Virtual Public Meeting: 2025 Resurfacing Program (County-wide)

WHEN: Friday, February 14, 2025, at 11 a.m.

WHERE: Online: https://bit.ly/wcrcprojectmeeting

By Touchtone Phone: (929) 205-6099, Meeting ID: 879 2332 8754

WHY: The Washtenaw County Road Commission (WCRC) will hold a virtual project information meeting regarding the planned County-wide Resurfacing Program taking place during the 2025 construction season.

During construction, traffic will be maintained under lane restrictions and flagging operations. During specific construction activities, the road may be closed, and a detour will be posted. WCRC estimates it will take approximately two/three weeks, on average, to complete each project, weather pending.

The virtual public meeting will be held via Zoom Friday, February 14, 2025, at 11 a.m. There will be a brief presentation followed by time for questions from the audience. A recording of the meeting will be posted to the project web page after the meeting.

Click here to learn more about joining the virtual meeting.

CONTACT: If you have any questions concerning these project, please contact Felix Weber-Bailey, Project Manager, (734) 327-6654, email [email protected], Kevin Dubnicki, Project Manager, (734) 327 -6693, email [email protected] and Ken Harris, Superintendent, (734) 327-6696, email [email protected]

WCRC will provide necessary reasonable auxiliary aids and services, such as signers for the hearing impaired and audiotapes or printed material being presented at the meeting, to individuals with disabilities upon a 5-business day notice. Individuals with disabilities requiring auxiliary aids or services should contact Tiffany Oliphant, communications manager, by phone (734) 327-6646 or by email [email protected].

ISSUE DATE: 02/04/25

February 4, 2025 Project Announcement: 2025 Resurfacing Program (County-wide)

The Washtenaw County Road Commission (WCRC) is excited to announce a $9.4 million investments in improving approximately 37 miles of paved and unpaved roads across Washtenaw County during the 2025 construction season. These important projects are made possible through a combination of funding sources, including the 2025-2028 Four-Year County-Wide Roads and Non-motorized Millage, Federal Funds, Township partnerships, and Michigan Transportation Funds (MTF). 

 “This year’s resurfacing program is just one of the ways WCRC is committed to protecting the county’s transportation infrastructure,” said Brent Schlack, P.E., Director of Engineering and County Highway Engineer. “The successful completion of these critical projects requires a blend of resources and collaboration.” 

 Construction is slated to begin in mid-April and will continue through the fall of 2025, weather permitting. As part of this program, WCRC will also undertake necessary forestry work to maintain the safety and integrity of the roadways. 

 For a list of the specific projects, funding details, and anticipated traffic impacts, please refer to the links provided below for each project location. 

Motorists will experience road closures with detours, daytime road closures, lane restrictions, and flagging operations. WCRC will maintain access for residents who live or work within the project limits during construction. 

WCRC will host a virtual public information meeting regarding the County-wide Resurfacing projects on February 14, 2025. WCRC will post project updates online at wcroads.org. Residents can subscribe to road work advisories and project updates here.

For specific questions on these projects, contact Felix Weber-Bailey, Project Manager, (734) 327-6654, email [email protected], Kevin Dubnicki, Project Manager, (734) 327 -6693, email [email protected] and Ken Harris, Superintendent, (734) 327-6696, email [email protected] 

Pictured is a map of our 2025 County-wide Resurfacing Program.

Contact information:
Kevin Dubnicki
    • (734) 327-6693
Receive Updates on the Project
Subscribe to Project Updates
Washtenaw County Road Commission
Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.