Location of roadwork:
Stony Creek, over Paint Creek, between Textile Rd and Whittaker Rd
Township:
Ypsilanti
When is the work being done:
2024
Description of work:
Bridge Removal, Bridge Replacement
Impact on Traffic:
Bridge Closure with Detour
Funding Source(s):
Federal, State Local Bridge Grant Program
Latest Updates
WHEN: Tuesday, March 5, 2024
WHERE: Stony Creek Rd between Textile Rd and Whittaker Rd in Ypsilanti Township
WHY: Completion of forestry work
BACKGROUND: On Tuesday, March 5, 2024, the Washtenaw County Road Commission (WCRC) re-opened Stony Creek Rd between Textile Rd and Whittaker Rd in Ypsilanti Township.
CONTACT: If you have any questions concerning this project, please contact Nate Murphy, Sr. Project Manager – D&C, (734) 327-6647 or [email protected]
ISSUE DATE: 03/05/24
WHEN: Monday, March 4, 2024
WHERE: Stony Creek Rd between Textile Rd and Whittaker Rd in Ypsilanti Township
WHY: Forestry
BACKGROUND: On Monday, March 4, 2024, a contractor for the Washtenaw County Road Commission (WCRC) will close Stony Creek Rd between Textile Rd and Whittaker Rd in Ypsilanti Township to perform forestry work for the upcoming bridge replacement project.
The forestry work is expected to take two days. However, all dates are tentative and subject to change due to weather conditions.
DETOUR: Click here for the detour map.
CONTACT: If you have any questions concerning this work, please contact Nate Murphy Sr. Project Manager – D&C, (734) 327-6647, or via email at [email protected]
ISSUE DATE: 02/29/24
WHEN: Friday, February 16, 2024
WHERE: Stony Creek Rd, over Paint Creek, between Textile Rd and Whittaker Rd in Ypsilanti Township
WHY: Permit – utility work
BACKGROUND: On Friday, February 16, 2024, DTE Gas re-opened Stony Creek Rd, over Paint Creek, between Textile Rd and Whittaker Rd in Ypsilanti Township.
CONTACT: If you have any questions concerning this project, please contact Nate Murphy, Sr. Project Manager – D&C, (734) 327-6647 or [email protected]
ISSUE DATE: 02/16/24
During the 2024 construction season, the Washtenaw County Road Commission (WCRC) plans to replace the Stony Creek Rd Bridge, over Paint Creek, between Textile Rd and Whittaker Rd in Ypsilanti Township. The bridge will be closed to all traffic during construction and a detour will be posted.
Thank you to those who were able to attend our virtual public construction information meeting on Tuesday, February 13, 2024. If you weren’t able to join us, click here to watch the meeting recording or check out the slide show. WCRC will continue to send out updates as the project progresses.
Questions about the project? Contact Nate Murphy, Sr. Project Manager – Design & Construction, at (734) 327-6647, or via email at murphyn@wcroads.org.
WHEN: Starting Tuesday, February 6, 2024
WHERE: Stony Creek Rd between Textile Rd and Whittaker Rd in Ypsilanti Township
WHY: Permit work – utility work
BACKGROUND: On Tuesday, February 6, 2024, DTE Gas will close Stony Creek Rd between Textile Rd and Whittaker Rd in Ypsilanti Township to relocate utilities.
The roadwork is expected to take approximately ten days. However, all dates are tentative and subject to change due to weather conditions.
DETOUR: Click here for the detour map.
CONTACT: If you have any questions concerning this work, please contact Nate Murphy, Sr. project manager – design & construction, (734) 327-6647, or via email at [email protected]
ISSUE DATE: 02/01/24
PROJECT: Stony Creek Rd Bridge Replacement Project
WHEN: Tuesday, February 13, 2024, at 12 p.m.
WHERE: Online: https://bit.ly/wcrcprojectmeeting
By Touchtone Phone: (929) 205-6099, Meeting ID: 879 2332 8754
WHY: The Washtenaw County Road Commission (WCRC) will hold a virtual project information meeting regarding the planned Bridge Replacement project on Stony Creek Rd in Ypsilanti Township.
During construction, Stony Creek Rd between Textile Rd and Whittaker Rd will be closed to ALL traffic and a detour will be posted. The closure is expected to be in place for approximately 12 weeks, weather pending.
The virtual public meeting will be held via Zoom on Tuesday, February 13, 2024, at 12 p.m. There will be a brief presentation followed by time for questions from the audience. A recording of the meeting will be posted to the project web page after the meeting.
Click here to learn more about joining the virtual meeting.
CONTACT: If you have any questions concerning this project, please contact Nate Murphy, project manager, at (734) 327-6647, or via email at [email protected].
WCRC will provide necessary reasonable auxiliary aids and services, such as signers for the hearing impaired and audiotapes or printed material being presented at the meeting, to individuals with disabilities upon a 5-business day notice. Individuals with disabilities requiring auxiliary aids or services should contact Tiffany Oliphant, communications manager, by phone (734) 327-6646 or by email [email protected].
ISSUE DATE: 01/17/24
During the 2024 construction season, the Washtenaw County Road Commission (WCRC) plans to replace the Stony Creek Rd Bridge, over Paint Creek, between Textile Rd and Whittaker Rd in Ypsilanti Township. The bridge will be closed to all traffic during construction and a detour will be posted.
Thank you to those who were able to attend our virtual public design information meeting on Tuesday, November 7, 2023. If you weren’t able to join us, click here to watch the meeting recording or check out the slide show. WCRC plans to hold a construction information meeting closer to the start of construction. WCRC will continue to send out updates as the project progresses.
Questions about the project? Contact Nate Murphy, project manager, at (734) 327-6647, or via email at murphyn@wcroads.org.
PROJECT: Stony Creek Rd Bridge Replacement Project
WHEN: Tuesday, November 7, 2023, at 11:30 a.m.
WHERE: Online: https://bit.ly/wcrcprojectmeeting
By Touchtone Phone: (929) 205-6099, Meeting ID: 879 2332 8754
WHY: The Washtenaw County Road Commission (WCRC) will hold a virtual project information meeting regarding the planned Bridge Replacement project on Stony Creek Rd, over Paint Creek, between Textile Rd and Whittaker Rd in Ypsilanti Township.
During construction, Stony Creek Rd will be Closed to all traffic and a detour will be posted. The closure is expected to be in place for 12 weeks, weather pending.
The virtual public meeting will be held via Zoom on Tuesday, November 7, 2023, at 11:30 a.m. There will be a brief presentation followed by time for questions from the audience. A recording of the meeting will be posted to the project web page after the meeting.
Click here to learn more about joining the virtual meeting.
CONTACT: If you have any questions concerning this project, please contact Nate Murphy, project manager, at (734) 327-6647, or via email at [email protected].
WCRC will provide necessary reasonable auxiliary aids and services, such as signers for the hearing impaired and audiotapes or printed material being presented at the meeting, to individuals with disabilities upon a 5-business day notice. Individuals with disabilities requiring auxiliary aids or services should contact Tiffany Oliphant, communications manager, by phone (734) 327-6646 or by email [email protected].
ISSUE DATE: 09/26/23