Location of roadwork:
Saline Waterworks Rd at Alber Rd
Township:
Lodi
When is the work being done:
2026
Description of work:
Culvert Replacement
Impact on Traffic:
Road Closure with Detour
Funding Source(s):
American Rescue Plan Act (ARPA)
Latest Updates
The Washtenaw County Road Commission (WCRC) removed and replaced the culvert on Saline Waterworks Rd at Alber Rd in Lodi Township. WCRC crews built the box culvert, then excavated and removed the existing culvert. During the week of August 3, WCRC crews finished backfilling, installing headwalls and wingwalls, and all restoration work.
The project is complete; the road has been re-opened to traffic.
WCRC is able to perform this project thanks to a Stormwater Grant and its partnership with the Washtenaw County Water Resources Commissioner’s Office and the Township.
If you have any questions regarding this project, contact please contact Neeko Robison, Project Manager, at (734) 327-6660, or via email at [email protected].

Pictured above is new culvert on Saline Waterworks Rd at Alber Rd in Lodi Township.
WHEN: Monday, July 27, 2026
WHERE: Intersection of Saline Waterworks Rd and Alber Rd in Lodi Township
WHY: Culvert replacement
BACKGROUND: On Monday, July 27, 2026, the Washtenaw County Road Commission (WCRC) will close the intersection of Saline Waterworks Rd and Alber Rd in Lodi Township for a culvert replacement.
The work is expected to take approximately ten days to complete. However, all dates are tentative and subject to change due to weather conditions.
The road will be closed to all through traffic. WCRC encourages drivers to use the detour.
DETOUR: Detour map
CONTACT: If you have any questions concerning this project, please contact Neeko Robison, Project Manager, at (734) 327-6660, or via email at [email protected].
ISSUE DATE: 07/22/2026