Location of roadwork:
Liberty Rd between Zeeb Rd and Wagner Rd
Township:
Scio
When is the work being done:
2025
Description of work:
Mill & Resurfacing
Impact on Traffic:
Flagging
Funding Source(s):
Four-Year Road and Non-Motorized Path Millage
Latest Updates
During the week of June 16, Cadillac Asphalt—the contractor for the Washtenaw County Road Commission (WCRC)—milled and resurfaced the asphalt on Liberty Road between Zeeb Road and Wagner Road in Scio Township. In addition, crews resurfaced seven county road approaches along this stretch of road.
In the coming weeks, crews will return to this section of Liberty Road to place gravel on the road shoulders and install permanent lane markings, depending on the contractor’s availability.
Later this summer, the contractor is scheduled to resurface the stretch of Liberty Road between Wagner Road and Scio Ridge Road, marking the completion of the project.
This work is funded by the Four-Year Roads and Non-Motorized Millage approved by voters last fall.
WCRC will continue to send updates as the project progresses. If you have questions contact Felix Weber, Project Manager – Design & Construction, (734) 327-6689, or via email at [email protected].
Pictured above the milling and resurfacing project on Liberty Rd in Scio Township.
WHEN: Wednesday, July 9, 2025
WHERE: Liberty Rd between Wagner Rd and Maple Rd in Scio Township
WHY: Road Resurfacing
BACKGROUND: On Wednesday, July 9, 2025, the Washtenaw County Road Commission (WCRC) will close Liberty Rd between Wagner Rd and Maple Rd in Scio Township for road resurfacing.
The road closure and road improvements are expected to take approximately six days to complete. However, all dates are tentative and subject to change due to weather conditions.
DETOUR: Click here for the detour map.
CONTACT: If you have any questions concerning this work, please contact Felix Weber, Project Manager, (734) 327-6689, or via email at [email protected]
ISSUE DATE: 07/02/25
WHEN: Thursday, June 5, 2025
WHERE: Liberty Rd between Zeeb Rd and Scio Ridge Rd in Scio Township.
WHY: Mill and Resurface
BACKGROUND: On Thursday, June 5, 2025, the Washtenaw County Road Commission (WCRC) will have lane restrictions on Liberty Rd between Zeeb Rd and Scio Ridge Rd in Scio Township for a mill and resurface.
The road will not be closed to traffic, but delays are likely due to lane restrictions. WCRC encourages motorists, emergency services and others to use an alternate route.
The mill and resurfacing work is expected to take approximately two weeks to complete. However, all dates are tentative and subject to change due to weather conditions.
CONTACT: If you have any questions concerning this work, please contact Felix Weber, Project Manager, (734) 327-6689, or via email at [email protected]
ISSUE DATE: 05/30/25
WHEN: Friday, February 14, 2025, at 11 a.m.
WHERE: Online: https://bit.ly/wcrcprojectmeeting
By Touchtone Phone: (929) 205-6099, Meeting ID: 879 2332 8754
WHY: The Washtenaw County Road Commission (WCRC) will hold a virtual project information meeting regarding the planned County-wide Resurfacing Program taking place during the 2025 construction season.
During construction, traffic will be maintained under lane restrictions and flagging operations. During specific construction activities, the road may be closed, and a detour will be posted. WCRC estimates it will take approximately two/three weeks, on average, to complete each project, weather pending.
The virtual public meeting will be held via Zoom Friday, February 14, 2025, at 11 a.m. There will be a brief presentation followed by time for questions from the audience. A recording of the meeting will be posted to the project web page after the meeting.
Click here to learn more about joining the virtual meeting.
CONTACT: If you have any questions concerning these project, please contact Felix Weber-Bailey, Project Manager, (734) 327-6654, email [email protected], Kevin Dubnicki, Project Manager, (734) 327 -6693, email [email protected] and Ken Harris, Superintendent, (734) 327-6696, email [email protected]
WCRC will provide necessary reasonable auxiliary aids and services, such as signers for the hearing impaired and audiotapes or printed material being presented at the meeting, to individuals with disabilities upon a 5-business day notice. Individuals with disabilities requiring auxiliary aids or services should contact Tiffany Oliphant, communications manager, by phone (734) 327-6646 or by email [email protected].
ISSUE DATE: 02/04/25
The Washtenaw County Road Commission (WCRC) is excited to announce a $9.4 million investments in improving approximately 37 miles of paved and unpaved roads across Washtenaw County during the 2025 construction season. These important projects are made possible through a combination of funding sources, including the 2025-2028 Four-Year County-Wide Roads and Non-motorized Millage, Federal Funds, Township partnerships, and Michigan Transportation Funds (MTF).
“This year’s resurfacing program is just one of the ways WCRC is committed to protecting the county’s transportation infrastructure,” said Brent Schlack, P.E., Director of Engineering and County Highway Engineer. “The successful completion of these critical projects requires a blend of resources and collaboration.”
Construction is slated to begin in mid-April and will continue through the fall of 2025, weather permitting. As part of this program, WCRC will also undertake necessary forestry work to maintain the safety and integrity of the roadways.
For a list of the specific projects, funding details, and anticipated traffic impacts, please refer to the links provided below for each project location.
Motorists will experience road closures with detours, daytime road closures, lane restrictions, and flagging operations. WCRC will maintain access for residents who live or work within the project limits during construction.
WCRC will host a virtual public information meeting regarding the County-wide Resurfacing projects on February 14, 2025. WCRC will post project updates online at wcroads.org. Residents can subscribe to road work advisories and project updates here.
For specific questions on these projects, contact Felix Weber-Bailey, Project Manager, (734) 327-6654, email [email protected], Kevin Dubnicki, Project Manager, (734) 327 -6693, email [email protected] and Ken Harris, Superintendent, (734) 327-6696, email [email protected].
Pictured is a map of our 2025 County-wide Resurfacing Program.