Fosdick Rd

Location of roadwork:
Fosdick Rd at the intersection of Tamarack Dr

Township:
Pittsfield

When is the work being done:
2023-2024

Description of work:
Culvert Replacement

Impact on Traffic:
Road Closure with Detour

Funding Source(s):
American Rescue Plan Act (ARPA)

Latest Updates

February 16, 2024 Project Update #3: Fosdick Rd Culvert Replacement (Pittsfield Twp)

On Thursday, February 15, 2024, the Washtenaw County Road Commission (WCRC) completed the culvert replacement on Fosdick Rd at the intersection of Tamarack Dr in Pittsfield Township, and the road was re-opened to traffic.  

We plan to have our crews return to the culvert location for repaving once the weather conditions are favorable for resurfacing. The schedule for this work is still yet to be determined. WCRC will send out updates as the project progresses.  

Have questions? Contact Ken Harris, Superintendent of Maintenance, at (734) 327-6696, or via email at  [email protected] 

Pictured is the location of where the new culvert was placed under Fosdick Rd at the intersection of Tamarack Dr in Pittsfield Township.
February 15, 2024 Road Reopened: Fosdick Rd (Pittsfield Twp)

WHEN: Thursday, February 15, 2024

WHERE: Fosdick Rd at the intersection of Tamarack Dr in Pittsfield Township

WHY: Completion of culvert replacement

BACKGROUND: On Thursday, February 15, 2024, the Washtenaw County Road Commission (WCRC) re-opened Fosdick Rd at the intersection of Tamarack Dr in Pittsfield Township.

CONTACT: If you have any questions concerning this project, please contact Ken Harris, Superintendent of Maintenance, at (734) 327-6696 or [email protected]

ISSUE DATE: 02/15/24

February 14, 2024 Project Update #2: Fosdick Rd Culvert Replacement (Pittsfield Twp)

We are making great progress with the culvert replacement on Fosdick Rd at the intersection of Tamarack Dr in Pittsfield Township.  

Over the last few days, our crews were able to remove the existing culvert and replace it with a new structure. We expect to complete this culvert replacement by the end of the week. Once this work is finished the road will be open to through traffic. The Washtenaw County Road Commission (WCRC) will continue to send out updates as the project progresses.  

Have questions about this project? Contact Ken Harris, Superintendent of Maintenance, at (734) 327-6696, or via email at [email protected] 

Pictured is the placement of the new culvert under Fosdick Rd at the intersection of Tamarack Dr in Pittsfield Township.  
February 8, 2024 Project Update #1: Fosdick Rd Culvert Replacement (Pittsfield Twp)

Great news Pittsfield Township! The Washtenaw County Road Commission (WCRC) plans to perform a culvert replacement on Fosdick Rd at the intersection of Tamarack Dr.  

In December 2023, Fosdick Rd was closed due to a crossroad culvert failure. The road has remained closed due to delays in equipment, materials and permits, as well as unfavorable weather conditions. WCRC is able to perform this project thanks to the American Rescue Plan Act (ARPA) and its partnership with the Washtenaw County Water Resources Commissioner’s Office and the Township. 

Next week, you should see our crews performing this culvert replacement on Fosdick Rd. Once the roadwork is complete, the road will be re-opened to traffic. WCRC will send out updates as the project progresses.  

Have questions? Contact Ken Harris, Superintendent of Maintenance, at (734) 327-6696, or via email at [email protected]  

Pictured is the failed crossroad culvert under Fosdick Rd at the intersection of Tamarack Dr in Pittsfield Township.
December 13, 2023 Road Closure with Detour: Fosdick Rd (Pittsfield Twp)

WHEN: Wednesday, December 13, 2023

WHERE: Fosdick Rd at the intersection of  Tamarack Dr in Pittsfield Township

WHY: Structural deterioration

BACKGROUND: On Wednesday, December 13, 2023, the Washtenaw County Road Commission (WCRC) closed Fosdick Rd at the intersection of Tamarack Dr in Pittsfield Township due to the structural deterioration of a crossroad culvert.

A schedule for repairs at this location is still yet to be determined. WCRC will send out updates as the project progresses.

DETOUR: Click here for the detour map.

CONTACT: If you have any questions concerning this work, please contact Nate Murphy, Sr. project manager, (734) 327-6647, or via email at [email protected]   

ISSUE DATE: 12/13/23

Contact information: