The contractor has set the beams in place, poured the concrete bridge deck, poured the concrete bridge approaches, and begun reconstructing the road.  Major items of work remaining to be completed include the completion of the road construction, building the bridge railings, installing guardrail and restoring the site.  The Road Commission has added work to this project to include the reconstruction of Ridge Rd from the bridge project to Mooreville Rd.  This work is currently ongoing.

Washtenaw County Road Commission
Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.