Week 3 Update: Scio Church/Wagner

The contractor has finished the installation of underground storm sewer and driveway culverts. This will be a short week of work since the MDOT holiday was 3 pm Friday, June 30 to 6 am Wednesday, July 5. The contractor’s focus will now transition toward cutting, shaping and rolling the roads in preparation for the placement of curb and gutter.

Thank you to everyone for their cooperation in staying out of the project construction zone. We understand it is an inconvenience to travel alternative routes to reach your destination.