DTE Gas Line Relocation on Baker Road

WHEN: Starting Monday, May 7, 2018

WHERE: Baker Road between Shield Road and Dan Hoey Road in Scio Township and the City of Dexter

WHY: DTE Gas Line Relocation

BACKGROUND: Starting Monday, May 7, 2018, DTE will begin a gas line relocation project ahead of the WCRC and City of Dexter Baker Road Roundabout Project starting later this summer.

During this gas line project there will be intermittent lane closures on Baker Road between Shield Road and Dan Hoey Road in Scio Township and the City of Dexter. WCRC encourages motorists, emergency services and others to use an alternate route.

The gas line replacement expected to take approximately 4 weeks, all dates are tentative and subject to change due to weather conditions. Baker Road will be closed to all traffic for the roundabout project once Dexter Community Schools have closed for the summer.

CONTACT: If you have any questions concerning this work, please contact Matt MacDonell, Assistant Director of Engineering, (734) 327-6688, or via email at [email protected]

Subscribe to Baker Road project updates online: https://www.wcroads.org/wcrc-project/baker-road-2/

ISSUE DATE: 05/07/18