We Need Your Help

By October 31, 2019Project Updates

Despite the rainy conditions, we are making steady progress on Phase 2 of the Ann Arbor-Saline Road concrete repair project.

We know this closure is very inconvenient for travelers in the area. We are doing everything we can to complete it as soon as possible but we need your help. We have noticed multiple cases of unauthorized personnel moving road closure barricades and driving through the work zone during the day and night. This must not continue. Not only it is a major safety hazard to drivers (there are big holes where concrete has been removed) and the roadworkers, it slows the progress of the work, as the barricades have to be reset each time. If you see a barrier out of place, please contact our main phoneline, (734) 761-1500, immediately.

We continue to actively monitor traffic signal timings in the area and will continue to make adjustments, as possible.

If you have any questions concerning this work, please contact Michele Ford, project manager, (734) 327-6652, or via email at [email protected].