was successfully added to your cart.

Sharon Valley Road Bridge

Location of roadwork:
Over the River Raisin between Prospect Hill Road and Lamb Road

Township:
Sharon

When is the work being done:
07/2/18 through Spring 2019

Description of work:
Bridge Replacement

Impact on Traffic:
Road closed with posted detour

Funding Source(s):
Federal

Latest Updates

March 22, 2019 A Pause in the Action

The reinforcing steel crew completed their work placing and tying the epoxy-coated resteel for the deck, bridge barrier railing, and sleeper slab (road approach item). Our contractor will be back onsite briefly next week to cover up the resteel.

Next step is the placement of the cast-in-place (CIP) concrete deck. Our contractor has elected to wait to pour the bridge deck until seasonal weight restrictions aka frost laws have been lifted. Seasonal weight restrictions may be lifted sometime in April, but this will depend upon weather conditions over the next few weeks.

When the work does resume, the focus will be on pouring the concrete bridge deck and the barrier rail. Once those items are completed, our contractor will then turn to the construction of the road approaches to the bridge.

If you have any questions, please contact Aaron Berkholz, project manager, at (734) 327-6648 or berkholza@wcroads.org.

It’s almost time to pour the concrete deck on the Sharon Valley Road Bridge

March 11, 2019 Next step? Rebar!

Our contractor continues to install the wood forms in preparation for the cast-in-place concrete deck. The reinforcing steel (rebar) subcontractor will likely be on site later this week, weather permitting. The warmer temperatures over the weekend are certainly a good sign but much of our work will continue to be dependent on the weather.

If you have any questions, please contact Aaron Berkholz, project manager, at (734) 327-6648 or berkholza@wcroads.org.

The Sharon Valley Road Bridge Deck

March 1, 2019 Forming the Deck

Building the forms for the concrete deck on the Sharon Valley Road Bridge

We continue to make progress on the new Sharon Valley Road Bridge in Sharon Township.

The concrete diaphragms and backwall were successfully poured in late-February. Our contractor is now working to create the forms for the concrete deck.  Once these items are in place, and if the weather cooperates, the concrete deck will be poured. After the deck has been successfully poured, the project will pause until the spring.

If you have any questions, please contact Aaron Berkholz, project manager, at (734) 327-6648 or berkholza@wcroads.org.

 

February 22, 2019 Under Wraps

February has certainly been an interesting month weather-wise. Work on the Sharon Valley Road Bridge has been “on again, off again” based on weather conditions.

The crew placed the cast-in-place concrete diaphragms and west end backwall today. In order to meet temperature specifications, tarps and insulating blankets were installed. See the photo below – the tarps were used to “tent” the bridge and heat was blown in underneath. Form, steel, and surface temperatures all checked out this morning.

The forecasted weather today, tomorrow, and Sunday have provided a good window. However, with the high winds expected on Sunday, the crew is planning on returning to the site tomorrow to remove the tarps hanging over the bridge. The newly placed concrete will remain wrapped in insulating blankets. The crew will begin placing forms for the cast-in-place concrete deck next week.

If you have any questions, please contact Aaron Berkholz, project manager, at (734) 327-6648 or berkholza@wcroads.org.

Today our contractor poured concrete for the diaphragms. The blankets were required to ensure proper concrete curing.

February 8, 2019 Supporting Act

Despite the weather, work continues at the Sharon Valley Road Bridge in Sharon Township. This week has been all about building additional supports for the beams that were placed in January. The contractor has been working on the concrete forms of the midspan diaphragms, supports built between the beams. We are hoping to pour the concrete for these diaphragms sometime next week if the weather cooperates.

After the diaphragms have been set, the bridge deck pouring can begin.

If you have any questions, please contact Aaron Berkholz, project manager, at (734) 327-6648 or berkholza@wcroads.org.

January 25, 2019 Beam are set!

All seven of the beams are now in their final resting position! Now the contractor’s crew is working on setting forms for the concrete “diaphragms” between the bridge beams.

Bridge crews will not be working next week due to the forecasted snow and cold temperatures. They plan on returning to work on Monday, February 4th.

If you have any questions, please contact Aaron Berkholz, project manager, at (734) 327-6648 or berkholza@wcroads.org.

Setting of the Beams on Sharon Valley Road Bridge

January 14, 2019 It’s (Almost) Beam Time!

This milder winter is certainly helping us out this season. We’ve been making steady progress, the west concrete abutment is in place and sand backfill was placed on Friday. Large stones aka riprap will likely be placed tomorrow.

The west steel sheet cofferdam will remain in place, as a measure to avoid any further disturbance of the underlying artesian condition. The crew will soon begin the process of cutting off and removing the top portion of the steel sheets (seen in the photo below).

Next up will be the concrete work for the west wingwalls and back wall, and placing the concrete beams across the river. Once these items are in place, and if the weather cooperates, the concrete deck will be poured. After the deck has been successfully poured, the project will pause until the spring.

Thanks for your patience on this project. If you have any questions, please contact Aaron Berkholz, project manager, at (734) 327-6648 or berkholza@wcroads.org.

Sharon Valley Road Bridge Construction – Photo taken January 11, 2019

December 27, 2018 Moving Water

We continue to make slow progress on the Sharon Valley Road Bridge reconstruction.

Last week, we de-watered the cofferdam and the artesian flows inside the cofferdam have been significantly reduced. Our contractor has now started prep work for the abutment/wingwalls. The reinforcing steel crew is expected to be onsite this week. Hopefully, we will be in a position to pour concrete the week after New Year’s, if the weather cooperates – pouring concrete diaphragms and a deck in freezing temperatures over open water is very challenging.

If you have any questions about this project, please contact Aaron Berkholz, project manager, at (734) 327-6648 or berkholza@wcroads.org.

Making Progress on the Sharon Valley Road Bridge cofferdam.

December 6, 2018 Slow but Sure

We are slowly making progress on addressing the artesian condition discovered earlier this Fall. In November, Spartan Specialties, our specialty subcontractor, successfully installed a “piezometer” well, allowing us to monitor the artesian flow.

The contractor also installed two well points just outside of the steel cofferdam enclosure in the northwest corner. We plan to use these pumps to direct the water away from our work.

You may have noticed that this effort required the construction of a temporary access road along the north side of the project. The temporary access will be removed once we complete the artesian-related work.

Unfortunately, this type of work is slow. Please know that we are working as hard as we can to remedy this difficult situation.

If you have any questions about this project, please contact Aaron Berkholz, project manager, at (734) 327-6648 or berkholza@wcroads.org.

October 25, 2018 We Have a Plan

We do have a plan but we won’t be able to complete the bridge replacement before winter.

In mid-September, we discovered an artesian condition that temporarily halted our construction. After much work, we now have devised an artesian remediation plan and our contractor has engaged specialty subcontractors to conduct the related work. We are expecting these contractors to begin working sometime in November. We cannot move forward with any other part of the bridge reconstruction until this has been addressed.

Considering typical timelines for the bridge work, and the limitations presented by winter weather conditions, completing the bridge and the road approach work will extend into the spring. Our hope is to get as much work as we can before winter and then come back in the spring. The bridge and road will remain closed until spring.

We know this is disappointing news. If you have any questions about this project, please contact Aaron Berkholz, the new project manager for this project. Aaron can be reached at (734) 327-6648 or berkholza@wcroads.org.

P.S. The maintenance work on the Austin Road bridge in Bridgewater Township should be completed this week, as long as the weather cooperates.

September 19, 2018 Well, Well, Well…We’ve found an Artesian

Unfortunately this week we have hit a snag in the replacement of the Sharon Valley Road bridge. While our contractor was constructing the west abutment (base where the bridge will connect), they discovered an unexpected artesian, a pressurized underground water pocket.

We are currently evaluating all the options to minimize the impacts of the artesian flow but this means that the project is now behind schedule. We are hoping to resume construction soon.

If you have any questions, please contact Kelly Jones, project manager, jonesk@wcroads.org or (734) 327-6647.

Sharon Valley Road Bridge September 17, 2018

The east abutment has been completed but we have hit a snag on the west abutment.

August 14, 2018 Sharon Valley Road Bridge Update

Our contractor is making great progress on the Sharon Valley Road Bridge!

The cofferdam (steel sheet enclosure) has been fully installed for both bridge abutments (foundations), the piles (steel pipes needed as part of the abutment support) have also been installed. The concrete pad has been poured for the east abutment and the next step will be to install the piles and concrete pad for the west abutment. Once that has been completed, we will start constructing both abutment walls.

Overall, we are on schedule. Thanks for your patience!

Sharon Valley Road Bridge Aerial View August 13, 2018

 Sharon Valley Road Bridge Aerial View August 13, 2018

July 18, 2018 Out With the Old & In With the New

As you can see, the Sharon Valley Rd Bridge replacement project is well underway.  The majority of the old bridge has been removed and our contractor, E.T. MacKenzie Company, continues to install the cofferdam (steel sheet enclosure) around the work area to aid in building the new foundations.

Please remember the road is closed to all traffic for the duration of the project and it is strongly recommended for all motorists to follow the posted detour route.  Thank you for your patience during this temporary inconvenience.

Please contact Kelly Jones at jonesk@wcroads.org or visit the project webpage at https://www.wcroads.org/wcrc-project/sharon-valley-road-bridge/ if you have any questions.

The old bridge has been removed!

It’s take some large equipment to replace a bridge

June 29, 2018 Road Closure: Sharon Valley Road (Sharon Twp)

WHEN: Monday, July 2, 2018

WHERE: Sharon Valley Road between Prospect Hill Road and Lamb Road in Sharon Township

WHY: Bridge replacement project

BACKGROUND: On Monday, July 2, 2018, a contractor for the Washtenaw County Road Commission (WCRC) will CLOSE Sharon Valley Road between Prospect Hill Road and Lamb Road in Sharon Township to replace the bridge over the River Raisin.

The road will be closed to all traffic during the bridge replacement project.  The WCRC expects the work to be completed by October 2018.  However, please be advised that due to weather conditions and/or unexpected conditions encountered during construction, all dates are tentative and subject to change.

The posted DETOUR for this closure is Wolf Lake Road, Austin Road and Sharon Hollow Road. Local traffic to and from adjacent properties located within the closed section of Sharon Valley Road will be maintained, but no traffic will be able to cross the bridge itself.

WCRC thanks you in advance for your patience during this bridge replacement project.

CONTACT: If you have any questions concerning this project, please contact Kelly Jones, (734) 327-6647, or via email at jonesk@wcroads.org.

For project specific updates and to subscribe to project updates please visit wcroads.org/wcrc-project/sharon-valley-road-bridge

For more information about all WCRC road closures visit wcroads.org/news/media-advisories

ISSUE DATE: 06/29/2018

May 31, 2018 Sharon Valley Road Bridge: Construction Info Meeting

This summer, the Washtenaw County Road Commission (WCRC) will be replacing the Sharon Valley Road Bridge over the River Raisin in Sharon Township.

Join WCRC Staff for a construction information meeting on Thursday, June 21 at 6 p.m. at the Sharon Township Hall, 18010 Pleasant Lake Road, Manchester, to learn more about the project.

During this project WCRC and its contractors will:

  • Replace the existing 72-foot bridge over the River Raisin with an 85-foot bridge.
  • Reconstruct the road approaches and install guardrail.

Project Timeline: WCRC’s contractor will begin on July 1, 2018 and will be completed by early October, depending on the weather.

Detours and Access: Sharon Valley Road will be closed throughout construction between Prospect Hill Rd and Lamb Rd, with traffic detoured to Sharon Hollow Road, Austin Road and Wolf Lake Road.

For more information:

Contact information:
Aaron Berkholz
    • 734-327-6648
Advisories and Detours
Receive Updates on the Project
Subscribe to Project Updates