Pleasant Lake Rd

Location of roadwork:
Between Sharon Hollow Rd and Smythe Rd

Township:
Sharon

When is the work being done:
April 7 - April 29

Description of work:
Mill & Resurfacing

Impact on Traffic:
Daytime road closures - emergency responders, local traffic including school buses will be provided access

Funding Source(s):
Michigan Transportation Fund (MTF)

Latest Updates

May 2, 2022 Daytime Road Closure: Pleasant Lake Rd (Sharon Twp)

WHEN: Monday, May 2, 2022

WHERE: Pleasant Lake Rd between Sharon Hollow Rd and Smythe Rd in Sharon Township

WHY: Shoulder placement

BACKGROUND: On Monday, May 2, 2022, contractors for the Washtenaw County Road Commission (WCRC) will close Pleasant Lake Rd between Sharon Hollow Rd and Smythe Rd in Sharon Township. Our contractors will be placing the new road shoulders following the road resurfacing. Placing road shoulders is the last phase of this project.

The road will reopen at the end of each day and remain open until work resumes the following morning.

The work is expected to take approximately two days to complete. However, all dates are tentative and subject to change due to weather conditions.

Access will be maintained for school buses, emergency responders and people who live or work within the work zone.

CONTACT: If you have any questions concerning this work, please contact Mike Bernbeck, project manager, (734) 327-6654, or via email at bernbeckm@wcroads.org.

ISSUE DATE: 05/02/22

April 13, 2022 Lane Restrictions: Pleasant Lake Rd (Sharon Twp)

WHEN: Starting on Monday, April 18, 2022

WHERE: Pleasant Lake Rd between Sharon Hollow Rd and Smythe Rd in Sharon Township

WHY: Road resurfacing

BACKGROUND: Starting on Monday, April 18, 2022, the Washtenaw County Road Commission (WCRC) will begin a road resurfacing project on Pleasant Lake Rd between Sharon Hollow Rd and Smythe Rd in Sharon Township. For the past week, WCRC crews have been making drainage improvements ahead of this road resurfacing project.

The road will not be closed to traffic, but delays are likely due to lane closures. WCRC encourages motorists, emergency services and others to use an alternate route.

The road resurfacing is expected to take approximately 2 weeks. However, all dates are tentative and subject to change due to weather conditions.

CONTACT: If you have any questions, please contact Mike Bernbeck, project manager, (734) 327-6654, or via email at bernbeckm@wcroads.org.

ISSUE DATE: 04/13/22

April 7, 2022 Daytime Road Closures: Pleasant Lake Rd (Sharon Twp)

WHEN: Starting today, Thursday, April 7, 2022

WHERE: Pleasant Lake Rd between Sharon Hollow Rd and Smythe Rd in Sharon Township

WHY: Drainage improvements

BACKGROUND: Starting today, Thursday, April 7, 2022, the Washtenaw County Road Commission (WCRC) will close Pleasant Lake Rd between Sharon Hollow Rd and Smythe Rd in Sharon Township for drainage improvements. The work is being completed ahead of a road resurfacing project planned to begin later this spring.

The road will reopen at the end of each day and remain open until work resumes the following morning.

The work is expected to take approximately two weeks to complete. However, all dates are tentative and subject to change due to weather conditions.

Access will be maintained for school buses, emergency responders and people who live or work within the work zone.

CONTACT: If you have any questions concerning this work, please contact Ken Harris, superintendent of maintenance, (734) 327-6696, or via email at harrisk@wcroads.org.

ISSUE DATE: 04/07/22

March 25, 2022 Daytime Road Closure: Pleasant Lake Rd (Sharon Twp)

WHEN: Starting Monday, March 28, 2022

WHERE: Pleasant Lake Rd between Sharon Hollow Rd and Smythe Rd in Sharon Township

WHY: Forestry

BACKGROUND: Starting Monday, March 28, 2022, the Washtenaw County Road Commission (WCRC) will close Pleasant Lake Rd between Sharon Hollow Rd and Smythe Rd in Sharon Township for forestry work. The work is being completed ahead of a resurfacing project planned for later this year.

The road will reopen at the end of each day and remain open until work resumes the following morning.

The work is expected to take approximately one week to complete. However, all dates are tentative and subject to change due to weather conditions.

Access will be maintained for residents and property owners who live or work within the work zone.

CONTACT: If you have any questions concerning this work, please contact Ken Harris, superintendent of maintenance, (734) 327-6696, or via email at harrisk@wcroads.org.

ISSUE DATE: 03/25/22

Contact information:
Ken Harris
    • (734) 327-6696