Platt Road Chipseal

Location of roadwork:
Between Willis Road and Bemis Road

Township:
York

When is the work being done:
Chip seal: Week of May 24, Fog seal: Week of July 19

Description of work:
Chipseal

Impact on Traffic:
Intermittent lane closures

Funding Source(s):
Michigan Transportation Fund (MTF)

Latest Updates

May 20, 2021 Road Work Advisory: Moon Rd & Platt Rd (York Twp)

WHEN: Starting on Monday, May 24, 2021

WHERE: – Platt Rd between Willis Rd and Bemis Rd
– Moon Rd between Willis Rd and Bemis Rd

WHY: Preventative maintenance – chip seal

BACKGROUND: Starting on Monday, May 24, 2021, the Washtenaw County Road Commission (WCRC) will begin preventative maintenance chip seal projects on Platt Rd between Willis Rd and Bemis Rd and Moon Rd between Willis Rd and Bemis Rd.

The work on these roads is expected to be completed by the end of the week. However, all dates are tentative and subject to change due to weather conditions.

Once the work is completed, drivers are advised to lower their speeds to 35 mph while the stone settles.

WCRC will return to this area in a few weeks to apply a fog seal on top of the chip seal and place permanent pavement markings.

CONTACT: If you have any questions, please contact Ken Harris, superintendent of maintenance, (734) 327-6696 or via email at harrisk@wcroads.org.

ISSUE DATE: 05/20/21

Contact information:
Ken Harris
    • (734)-327-6696