Platt Road

Location of roadwork:
Between Judd Rd and Willis Rd

Township:
York

When is the work being done:
April 28 - May 7

Description of work:
Mill & Resurfacing

Impact on Traffic:
Intermittent lane closures

Funding Source(s):
Township

Latest Updates

April 27, 2021 Lane Restrictions- Platt Rd (York Twp)

WHEN: Starting Wednesday, April 28, 2021

WHERE: Platt Rd between Judd Rd and Willis Rd in York Township

WHY: Road resurfacing

BACKGROUND: Starting Wednesday, April 28, 2021, the Washtenaw County Road Commission (WCRC) will begin shoulder work in preparation for resurfacing Platt Rd between Judd Rd and Willis Rd in York Township.

WCRC expects to begin milling the road surface later this week and hopes to pave next week.

Platt Rd will not be closed to traffic, but delays are likely due to lane restrictions. WCRC encourages motorists, emergency services and others to use an alternate route.

The road improvements are expected to take approximately 10 days. However, all dates are tentative and subject to change due to weather conditions.

WCRC will return to this area in 2022 to pulverize and resurface Platt Rd between the City of Milan limits and Willow Rd.

CONTACT: If you have any questions concerning this work, please contact Mike Bernbeck, (734) 327-6654, or via email at bernbeckm@wcroads.org

ISSUE DATE: 04/27/21

Contact information:
Mike Bernbeck
    • (734) 327-6654
Helpful Links