Packard Road

Location of roadwork:
Between Carpenter Road and Courtland Street

Township:
Pittsfield, Ypsilanti

When is the work being done:
Carpenter Rd to Golfside Rd: May 10 - mid June, Golfside Rd to Courtland St: August 10 - 21

Description of work:
Mill & Resurfacing

Impact on Traffic:
Lane closures and periodic sidewalk closures

Funding Source(s):
Federal, Four-Year Road and Non-Motorized Path Millage

Latest Updates

August 5, 2021 Lane Closures: Packard Rd (Ypsilanti Twp)

WHEN: Starting Tuesday, August 10, 2021

WHERE: Packard Rd between Golfside Rd and the City of Ypsilanti in Ypsilanti Township

WHY: Road resurfacing

BACKGROUND: On Tuesday, August 10, 2021, the Washtenaw County Road Commission (WCRC) will begin a road resurfacing project on Packard Rd between Golfside Rd and the City of Ypsilanti in Ypsilanti Township.

The road will not be closed to traffic, but delays are likely due to lane closures. WCRC encourages motorists, emergency services and others to use an alternate route.

The road improvements are expected to take approximately one week. However, all dates are tentative and subject to change due to weather conditions.

Sidewalks and crossing signals will be impacted periodically by this work.

CONTACT: If you have any questions concerning this work, please contact Mike Bernbeck, (734) 327-6654, or via email at bernbeckm@wcroads.org.

ISSUE DATE: 08/05/21

May 6, 2021 Lane Closures: Packard Rd (Pittsfield Twp)

WHEN: Starting Monday, May 10, 2021

WHERE: Packard Rd between Carpenter Rd and Golfside Rd in Pittsfield Township

WHY: Road resurfacing

BACKGROUND: On Monday, May 10, 2021, the Washtenaw County Road Commission (WCRC) will begin a road resurfacing project on Packard Rd between Carpenter Rd and Golfside Rd in Pittsfield Township.

The road will not be closed to traffic, but delays are likely due to lane closures. WCRC encourages motorists, emergency services and others to use an alternate route.

The road improvements are expected to take approximately 6 weeks. However, all dates are tentative and subject to change due to weather conditions.

Sidewalks and crossing signals will be impacted periodically by this work.

CONTACT: If you have any questions concerning this work, please contact James Hui, (734) 327-6660, or via email at huij@wcroads.org.

ISSUE DATE: 05/06/21

Contact information:
James Hui
    • (734) 327-6660