North Territorial Road Chip Seal

Location of roadwork:
Between M-52 and Hankerd Road

Township:
Dexter, Lyndon

When is the work being done:
Chip seal: Week of 6/21, Fog seal: Week of August 2

Description of work:
Chipseal

Impact on Traffic:
Intermittent lane closures

Funding Source(s):
Four-Year Road and Non-Motorized Path Millage

Latest Updates

August 4, 2021 Daytime Road Closure: N Territorial Rd (Dexter, Lyndon Twps)

WHEN: Starting on Thursday, August 5, 2021

WHERE: Starting on the following roads in Dexter and Lyndon Townships:

  • N Territorial Rd between M-52 and Hankerd Rd

WHY: Preventative maintenance – fog seal

BACKGROUND: Starting on Thursday, August 5, 2021, the Washtenaw County Road Commission (WCRC) will begin preventative maintenance fog seal projects on sections of the following roads in Dexter and Lyndon Townships: N Territorial Rd.

Fog seal is another thin layer of liquid asphalt placed on top of a recent chip seal that helps to seal in the chips and further protect the pavement.

The work on these roads is expected to be completed by the end of this week. However, all dates are tentative and subject to change due to weather conditions.

The work will be conducted under a combination of lane restrictions and daytime closures to allow the fog seal to cure. A contractor for WCRC will return to this area in a few weeks to place permanent pavement markings.

CONTACT: If you have any questions, please contact Ken Harris, superintendent of maintenance, (734) 327-6696 or via email at harrisk@wcroads.org.

ISSUE DATE: 08/04/21

June 17, 2021 Lane Restrictions: N Territorial Rd (Lyndon, Dexter Twps)

WHEN: Starting on Monday, June 21, 2021

WHERE: N Territorial Rd between M-52 and Hankerd Rd in Lyndon and Dexter Townships

WHY: Preventative maintenance – chip seal

BACKGROUND: Starting on Monday, June 21, 2021, the Washtenaw County Road Commission (WCRC) will begin a preventative maintenance chip seal project on N Territorial Rd between M-52 and Hankerd Rd in Lyndon and Dexter Townships.

The work on this road is expected to be completed by the end of the week. However, all dates are tentative and subject to change due to weather conditions.

Once the work is completed, drivers are advised to lower their speeds to 35 mph while the stone settles.

WCRC will return to this area in a few weeks to apply a fog seal on top of the chip seal and place permanent pavement markings.

CONTACT: If you have any questions, please contact Ken Harris, superintendent of maintenance, (734) 327-6696 or via email at harrisk@wcroads.org.

ISSUE DATE: 06/17/21

Contact information:
Ken Harris
    • (734) 327-6696
Helpful Links