was successfully added to your cart.

Cart

Miller Road Bridge and Roundabout

Location of roadwork:
Miller Road between East Delhi Road and Wagner Road

Township:
Scio

When is the work being done:
Roundabout: 7/14 through mid-October; Bridge: mid-October through early-December

Description of work:
Bridge Replacement, Mill & Resurfacing, Roundabout

Impact on Traffic:
Miller Road is closed to through traffic between E. Delhi Road and Wagner Road

Funding Source(s):
Federal, Michigan Transportation Fund (MTF), State Local Bridge Grant Program

Latest Updates

September 21, 2020 Miller/Wagner: Going in Circles

Looks like another beautiful week for roundabout construction! Our contractor continues to make steady progress on the new Miller Road roundabout and bridge in Scio Township.

Miller/Wagner Roundabout: Our contractor poured the roundabout’s central island and splitter island concrete curbs last week. Once the concrete has cured, they will pour and stamp concrete inside the islands, hopefully later this week. They are also working on grading the outer slopes and placing grass seed in these areas.

Bridge Over Honey Creek: Utility relocation work continues near the Miller Road bridge over Honey Creek.

Questions? Contact Nate Murphy, project manager, (734) 327-6647, murphyn@wcroads.org.

photo of new curb on Miller and Wagner splitter island

photo of slope restoration at Miller and Wagner

September 11, 2020 Miller/Wagner: Island Time

Although it was a short week with the holiday and some rain, we continue to make progress on the new Miller Road roundabout and bridge in Scio Township.

Miller/Wagner Roundabout: Our contractor is preparing the interior of the roundabout for more concrete. They will first pour the interior curb for the central island and splitter islands. Once the concrete has cured, they will pour and stamp concrete inside the islands.

Bridge Over Honey Creek: Utility relocation work continues near the Miller Road bridge over Honey Creek.

Right now, we are hoping to have the roundabout completed by mid-October and the bridge completed by early-December if the weather cooperates. Questions? Contact Nate Murphy, project manager, (734) 327-6647, murphyn@wcroads.org.

photo of roundabout grading

September 3, 2020 Miller/Wagner: Taking Shape

It was another productive week on Miller Road in Scio Township as we work on a bridge replacement and new roundabout.

Roundabout: Our contractor started pouring concrete curbs this week. They will start on the inner curbs and center island of the roundabout soon.

Bridge Over Honey Creek: Utility relocation work continues near the Miller Road bridge over Honey Creek. Our contractor also started clearing brush near the bridge.

Questions? Contact Nate Murphy, project manager, (734) 327-6647, murphyn@wcroads.org.

drone photo of miller/wager roundabout curbs

August 25, 2020 Miller/Wagner: Bridge Work Starting Soon

Phew! There is a lot going on this summer on Miller Road in Scio Township including a bridge replacement, new roundabout and road resurfacing. Here’s the latest:

Roundabout

Our contractor continues to make progress on the new roundabout under construction at the intersection of Miller Road and Wagner Road. This week, they are laying the aggregate base in preparation for curbs. We are hoping to pour the concrete curb next week if the weather cooperates. The intersection remains closed to all traffic.

Bridge Over Honey Creek

Utility relocation work continues near the Miller Road bridge over Honey Creek. Due to this relocation work, the road closure for through-traffic has been extended. Miller Road is closed to through-traffic between E. Delhi Road and Wagner Road. Our contractor plans to begin removing the asphalt pavement from the bridge deck in the coming weeks.

Access for Residents Living within Construction Limits

We will not block you from your homes/driveways during these projects. Residents who live on Miller Road between E. Delhi Road and Wagner Road will continue to be provided access to their homes/driveways via west Miller Road until the roundabout is reopened, even when our contractor begins removing asphalt from the bridge deck.

Questions? Contact Nate Murphy, project manager, (734) 327-6647, murphyn@wcroads.org.

photo of grading on Miller/Wagner

Our contractors are working on the road base in preparation for curb.

August 11, 2020 Miller/Wagner: Water Management

Our contractor has really “dug” into the new roundabout project at the intersection of Miller Rd and Wagner Rd in Scio Township. They began installing the storm sewer last week and should finish it this week. They also continue to grade the site in preparation for the concrete curb.

Questions? Contact Nate Murphy, project manager, (734) 327-6647, murphyn@wcroads.org.

photo of storm sewer work at Miller and Wagner

July 22, 2020 Miller/Wagner: Making Room for Roundabout

It has been a very productive first construction week at the intersection of Miller Rd and Wagner Rd in Scio Township. Utility contractors have nearly wrapped up their relocation work. Our road construction contractor removed the existing asphalt pavement last week and this week has started clearing the area in preparation for excavation.

Questions? Contact Nate Murphy, project manager, (734) 327-6647, murphyn@wcroads.org.

Miller/Wagner prep photo

As utilities finish up relocating their facilities, our contractor has begun prepping the site for excavation.

July 14, 2020 Miller/Wagner: Intersection Closed for Construction

The intersection of Miller Road and Wagner Road in Scio Township is officially closed. The closure is expected to last approximately 8 weeks as our contractor constructs a single-lane roundabout.

Property owners and residents who live or work within the project area will be provided access by the contractor, however, no traffic will be allowed to traverse through the intersection during roundabout construction. The bridge replacement project over Honey Creek will begin later this summer.

Questions? Contact Nate Murphy, project manager, (734) 327-6647, murphyn@wcroads.org.

Miller Wagner Closure

July 8, 2020 Road Closure: Intersection of Miller Road and Wagner Road (Scio Twp)

WHEN: Starting Monday, July 13, 2020

WHERE: Intersection of Miller Road and Wagner Road in Scio Township

WHY: Roundabout construction

BACKGROUND: On Monday, July 13, 2020, the Washtenaw County Road Commission (WCRC) will close the intersection of Miller Road and Wagner Road in Scio Township to construct a single-lane roundabout.

Once the intersection is closed and construction begins, the intersection will be closed to all traffic, including bicyclists and pedestrians, for approximately 8 weeks.

DETOUR: Click here for the posted detour.

CONTACT: If you have any questions concerning this work, please contact Nate Murphy, project manager and bridge engineer, (734) 327-6647, or via email at murphyn@wcroads.org.

ISSUE DATE: 07/08/20

June 30, 2020 Miller/Wagner: Closure to Start July 13

Utility relocation work continues near the intersection of Miller Road and Wagner Road in Scio Township. This work is in preparation for our roundabout and bridge project and will continue for the next two weeks. Currently, our contractor is planning to close the intersection to begin roundabout construction on Monday, July 13. This date could change as we get closer.

Once the intersection is closed, it will be closed for approximately 8 weeks. Property owners and residents who live or work within the project area will be provided access by the contractor, however, no traffic will be allowed to traverse through the intersection during roundabout construction or cross the bridge during the bridge replacement project. The bridge project over Honey Creek will begin later this summer.

Questions? Contact Nate Murphy, project manager, (734) 327-6647, murphyn@wcroads.org.

June 25, 2020 Road Closure: Miller Road (Scio Twp)

WHEN: Thursday, June 25, 2020

WHERE: Miller Road, just west of Wagner Road in Scio Township

WHY: Road closure

BACKGROUND: On Thursday, June 25, 2020 at noon, AT&T unexpectedly had to close Miller Road, just west of Wagner Road in Scio Township as they relocate their facilities in advance of WCRC’s roundabout project. The closure is expected to last until tomorrow.

There is also gas line relocation work taking place near the Miller Road bridge over Honey Creek west of the intersection.

Residents and property owners who live or work within the road closure will be provided access to their homes by the traffic control crews in the area. All other traffic is asked to avoid the area if possible.

CONTACT: If you have any questions concerning this closure, please contact Nate Murhpy, project manager and bridge engineer, (734) 327-6647, murphyn@wcroads.org

ISSUE DATE: 06/25/20

May 26, 2020 Virtual Public Meeting Notice: Miller Rd and Wagner Rd Projects (Scio Twp)

WHAT: Miller Road Bridge and Roundabout Project Virtual Meeting

WHEN: Wednesday, June 10, 2020, 10 a.m.

WHERE: Online: https://bit.ly/wcrcprojectmeeting

By Touchtone Phone: (929) 205-6099, Meeting ID: 879 2332 8754

WHY: The Washtenaw County Road Commission will hold a virtual meeting to share information about the roundabout to be built at the intersection of Miller Road and Wagner Road and the Miller Road bridge replacement project in Scio Township. Construction of the roundabout is expected to begin in late-June and bridge construction will begin in July.

The virtual meeting will be held through Zoom on Wednesday, June 10, 2020 at 10 a.m. There will be a brief presentation followed by time for questions from the audience. A recording of the meeting will be posted to the project web page after the meeting ends.

Click here to learn more about joining the virtual meeting.

CONTACT: If you have any questions concerning this project, please contact Nate Murphy, bridge engineer, (734) 327-6647, murphyn@wcroads.org.

WCRC will provide necessary reasonable auxiliary aids and services, such as signers for the hearing impaired and audiotapes or printed material being presented at the meeting, to individuals with disabilities upon a 5-business day notice.

Individuals with disabilities requiring auxiliary aids or services should contact Emily Kizer, communications manager, by phone (734) 327-6646 or by email kizere@wcroads.org.

ISSUE DATE: 05/26/2020

May 20, 2020 Miller Rd and Wagner Rd: Utility Relocations Begin

Earlier today, DTE began its utility pole relocation work on Miller Road and Wagner Road ahead of our roundabout and bridge project this summer. The road will remain open during DTE’s work but there will be intermittent lane restrictions for approximately one week (weather pending).

Roundabout construction at the intersection of Miller Road and Wagner Road is still expected to begin in June and the bridge replacement work will start on or after July 1. WCRC is hosting a virtual construction information meeting on Wednesday, June 10 at 10 a.m. to share details about construction and answer audience questions. Click here to learn more about joining the virtual meeting. 

Questions? Contact Nate Murphy, project manager, (734) 327-6647, murphyn@wcroads.org.

March 6, 2020 Miller Rd and Wagner Rd: Tree Removals Wrapping Up

Our contractor is planning to complete the required tree removals on Miller Road early next week. They ended up being able to conduct the work under lane restrictions instead of a full road closure. Please continue to use caution around the work zone as they finish up.

Roundabout construction at the intersection of Miller Road and Wagner Road is still expected to begin later this spring. We will issue another update prior to the start of construction.

Questions? Contact Nate Murphy, project manager, (734) 327-6647, murphyn@wcroads.org.

February 19, 2020 Lane Restrictions: Intersection of Miller Rd and Wagner Rd (Scio Twp)

WHEN: Starting Monday, February 24, 2020

WHERE: Intersection of Miller Road and Wagner Road in Scio Township

WHY: Tree removals

BACKGROUND: Starting Monday, February 24, 2020, the Washtenaw County Road Commission (WCRC) and its contractor will begin tree removals at the intersection of Miller Road and Wagner Road in Scio Township. These removals are in preparation for the intersection improvement project planned this spring/summer.

Forestry work at the intersection is expected to last 5 days, however all dates are tentative and subject to change due to weather conditions. The intersection will not be closed to traffic, but delays are likely due to lane restrictions.

FYI: Starting the week of March 2, Miller Road between E. Delhi Road and N. Wagner Road will be closed to through traffic while WCRC’s contractor conducts tree removals for the bridge replacement project this summer. Another work advisory will be posted prior to this closure.

CONTACT: If you have any questions concerning this work, please contact Nate Murphy, project manager, (734) 327-6647, murphyn@wcroads.org

ISSUE DATE: 02/19/20

January 28, 2020 Miller Rd: Tree Removals To Begin

This summer, we will replace an aging bridge on Miller Road over Honey Creek and construct a single-lane roundabout at the intersection of Miller Road and Wagner Road in Scio Township.

In preparation for this summer work, our contractor will begin the necessary tree removals in the coming weeks. We are planning to remove approximately 100 trees that are in conflict with the planned improvements (roundabout and bridge). We worked with our consultants during design to minimize tree removals wherever possible.

Miller Road will remain open to traffic during the tree work but there may be lane restrictions. We will issue a road advisory ahead of these lane restrictions. All tree removal work will be completed by March 31, 2020.

For specific questions on this project contact Nate Murphy, project manager, (734) 327-6647, murphyn@wcroads.org.

October 1, 2019 Project Info Meeting: Miller Road Improvements

WHAT: Miller Road Bridge and Roundabout Project Meeting

WHEN: Tuesday, October 15, 2019 from 6 – 7 p.m.

WHERE: WCRC’s Administrative Office, 555 N. Zeeb Road, Ann Arbor

WHY: The Washtenaw County Road Commission (WCRC) will hold a public meeting on Tuesday, October 15, 2019 from 6 – 7 p.m. to provide information and answer questions about the road improvements planned in 2020 on Miller Road in Scio Township.

WCRC will be constructing a roundabout at the intersection of Miller Road and Wagner Road beginning May 2020. The intersection will be closed to all traffic during this project. Then, starting on July 1, 2020, WCRC will replace the bridge over Honey Creek on Miller Road. The bridge will be closed to all traffic until the end of August.

CONTACT: Visit www.wcroads.org/wcrc-project/miller-road-bridge-and-roundabout/ for more information and to subscribe to project updates.

If you have any questions, please contact Nate Murphy, project manager, (734) 327-6647, murphyn@wcroads.org.

WCRC will provide necessary reasonable auxiliary aids and services, such as signers for the hearing impaired and audiotapes or printed material being considered at the meeting, to individuals with disabilities upon a 7-business day notice to WCRC. Individuals with disabilities requiring auxiliary aids or services should contact Emily Kizer, communications manager, by phone (734) 327-6646, by email kizere@wcroads.org, by fax (734) 761-3737 or by mail at WCRC, 555 N. Zeeb Road, Ann Arbor, MI 48103.

ISSUE DATE: 10/01/2019

September 4, 2019 Project Announcement: Miller Rd Bridge & Roundabout (Scio Twp)

The Washtenaw County Road Commission (WCRC) is excited to announce a three-part project planned for the 2020 construction season on Miller Road in Scio Township. The project will consist of the following:

  • The Miller Road bridge over Honey Creek will be replaced
  • A single-lane roundabout will be constructed at the intersection of Miller Road and Wagner Road
  • The road segment between the bridge and intersection will be resurfaced

 Why this segment of road?

Bridge

The Miller Road bridge over Honey Creek was built in the 1930s and has reached the end of its design life. It has been weight-restricted for many years and needs to be replaced. WCRC received a Local Bridge Program Grant from the Michigan Department of Transportation to replace this bridge in 2020.

Roundabout

WCRC monitors numerous intersections across the county for congestion and safety. The intersection of Miller Road and Wagner Road is heavily congested during peak hours of travel. A roundabout is an ideal solution to help alleviate this congestion during peak hours while minimizing impacts to surrounding properties.

While the road is closed for these projects, WCRC will resurface the road between the bridge and the new roundabout.

Both the bridge and roundabout projects will require some trees to be removed along the roadway. WCRC is working with its consultant to minimize tree removals whenever possible. More information on tree removal plans will be provided as the design process continues.

When will this project be completed?

Construction is expected to occur in 2020.

The roundabout will be constructed first, WCRC estimates that it will take 6 – 8 weeks to build the roundabout, weather pending. During this time, the intersection will be completely closed to all traffic and a detour will be posted.

Once the roundabout has been completed, WCRC will begin the bridge project. Due to state environmental restrictions, bridgework must begin after July 1. The bridgework is expected to take 2 – 3 months, the bridge location will be completely closed to all traffic during this period and a detour will be posted.

The road between the bridge and roundabout will be resurfaced while the road is closed.

How can I get more information? WCRC will hold a public information meeting about this project later this fall. WCRC will also post project updates online and on its Facebook and Twitter pages.

Visit the project page to subscribe to project updates: www.wcroads.org/wcrc-project/miller-road-bridge-and-roundabout/

For specific questions on this project contact Matt MacDonell, (734) 327-6688, macdonellm@wcroads.org