McGregor Road Chipseal

Location of roadwork:
Dexter-Pinckney Road to the county line

Township:
Dexter

When is the work being done:
08/25

Description of work:
Chipseal

Impact on Traffic:
Intermittent Lane Closures

Funding Source(s):
Michigan Transportation Fund (MTF)

Latest Updates

August 24, 2020 Lane Restrictions: McGregor Road (Dexter Twp)

WHEN: Starting Tuesday, August 25, 2020

WHERE: McGregor Road between Dexter-Pinckney Road and the county line in Dexter Township

WHY: Preventative maintenance – fog seal

BACKGROUND:    Starting Tuesday, August 25, 2020, the Washtenaw County Road Commission (WCRC) will apply a fog seal on McGregor Road between Dexter-Pinckney Road and the county line in Dexter Township.

Fog seal is another thin layer of liquid asphalt placed on top of a recent chip seal that helps to seal in the chips and further protect the pavement. This work will be conducted under lane restrictions and all vehicles must stay off the fog seal while it cures. Curing time depends on several factors including weather.

This work is expected to be completed in one day. However, all dates are tentative and subject to change due to weather conditions.

Once the fog seal has been completed, WCRC’s contractor will return to place permanent pavement markings in the coming weeks.

CONTACT: If you have any questions concerning this work, please contact Ken Harris, superintendent of maintenance, (734) 327-6696, harrisk@wcroads.org.

ISSUE DATE: 08/24/20

 

Contact information:
Ken Harris or Adam Lape
    • (734) 327-6696 or (734) 327-6697