McGregor Rd Bridge

Location of roadwork:
McGregor Rd, over Portage Lake outlet, between Dexter-Pinckney Rd and Huron St

Township:
Dexter

When is the work being done:
TBD

Description of work:
Bridge Preservation, Preventative Maintenance

Impact on Traffic:
Intermittent lane restrictions

Funding Source(s):
Michigan Transportation Fund (MTF)

Latest Updates

July 20, 2023 Project Update: Nearly Complete!

Construction on the McGregor Rd bridge, over Portage Lake outlet, between Dexter-Pinckney Rd and Huron St in Dexter Township, is nearly complete.

By the end of this week, the contactor will complete the epoxy overlay on the bridge deck surface. However, all dates are tentative and subject to change based on weather conditions. Once the epoxy overlay is completed, all restrictions will be lifted.

Have questions about the project? Contact Nate Murphy, project manager, at (734) 327-6647, or via email at murphyn@wcroads.org.

Pictured is the epoxy process of the McGregor Rd bridge, located over the Portage Lake outlet, between Dexter-Pinckney Rd and Huron St in Dexter Township.
July 10, 2023 Lane Restrictions: McGregor Rd (Dexter Twp)

WHEN: Monday, July 10, 2023

WHERE: McGregor Rd, over Portage Lake outlet, between Dexter-Pinckney Rd and Huron St

WHY: Bridge preventative maintenance

BACKGROUND: Starting Monday, July 10, 2023, the Washtenaw County Road Commission (WCRC) will begin an epoxy overlay on the McGregor Rd, over Portage Lake outlet, between Dexter-Pinckney Rd and Huron St in Dexter Township.

The road will not be closed to traffic, but delays are likely due to lane restrictions and a flagging operation. WCRC encourages motorists, emergency services and others to use an alternate route.

The road improvements are expected to take approximately one week. However, all dates are tentative and subject to change due to weather conditions.

CONTACT: If you have any questions concerning this work, please contact Nate Murphy, project manager, at (734) 327-6647, or via email at murphyn@wcroads.org